The Green Premium : GCC & India Hydrogen Outlook
Volge
Quarterly
Q3 2026 · The GCC & India Hydrogen issue
Sovereign AI
Owning the stack
Foundation
Data before AI
Vision 2030
Vision 2030, revised

The Green
Premium

Gigaproject capital is moving ahead of offtake: where hydrogen economics close first, and who funds the gap.

volge.com/quarterlyComplimentary editionISSN 2977-4404 · 04

Volge Quarterly is Volge's signature series, published every quarter for enterprise customers. Each edition takes one subject, sets out where it currently stands on the published record, and makes a set of dated, falsifiable judgements on where it is going, written to give a buyer something firmer than a forecast: every figure carries its source and its date, every judgement carries the date on which it resolves, and the following year's edition grades each one hit, missed or partial.

2027 is the year the green premium meets its first real test. The Gulf ships first production, but its near-term volume is blue, not green. India has awarded a pipeline and commissioned almost none of it. Two bets on the same fuel, read in the physical world rather than the press release.

Figures carry their basis and their date. Where published estimates disagree, the range is given and the basis named rather than averaged away, and where a widely quoted number does not survive checking it is corrected here rather than repeated. Every chart plots a figure stated in the text, and nothing is projected beyond what a named source projects.

Contents

  1. 02The state of the sector
  2. 02The year the green premium is put to the test
  3. 03A contracting pipeline, and a widening premium
  4. 03Green against grey and blue, per kilogram
  5. 04Awarded capacity against signed demand
  6. 04The two models
  7. 04Saudi Arabia: NEOM, the one bankable green flagship
  8. 05Oman: Hydrom, blocks auctioned ahead of demand
  9. 05UAE & Qatar: blue first, green offshored
  10. 06The Mission and SIGHT: awarded at scale, commissioned barely
  11. 06The Indian field: nineteen awardees, one table
  12. 06The demand anchors: fertiliser, refining and steel
  13. 07RFNBO, CBAM and the buyers in Europe and Asia
  14. 07Offtake, cost, power, water, financing
  15. 08The forces shaping the year
  16. 08Green or grey: the cost gap, and why it is widening
  17. 08Two models of the same bet: export against demand
  18. 09Offtake is the bottleneck: the binding constraint of 2027
  19. 09The RFNBO passport: Europe’s rulebook as the gate
  20. 10Fable risk: the project that does not ship
  21. 10The buyer's ground
  22. 10The pipeline, sorted by what is actually true
  23. 12Offtake, the binding constraint, proved by name
  24. 14The only prices anyone has published
  25. 15What the premium actually is, and why the number moves
  26. 17Who is actually obliged to buy
  27. 19Europe's rulebook as the real gate
  28. 20The reality check: a sector revising itself downward
  29. 21Subsidy, and what it is worth to a buyer
  30. 23The dated calendar, 2026 to 2030
  31. 26The Calls
  32. 26The Calls: 2027, at a glance
  33. 26Calls one to three
  34. 27How the Calls are made
  35. 28The year, read
  36. 28By domain: technology, markets, regulation, delivery
  37. 28Three scenarios for 2027
  38. 29The watchlist: the signals that seed next year’s Calls
  39. 29Project data appendix
  40. 30Sources and glossary
Volge Quarterly is Volge's signature series, published every quarter for enterprise customers.
Volge · Panache Editions · The GCC & India Hydrogen edition
GCC & India HydrogenVolge Quarterly01 •

The state of the sector

A market whose defining number turned the wrong way. The announced-for-2030 pipeline of low-emission hydrogen fell for the first time: from 49 to 37 Mtpa in a single year, and again to 27 Mt in the 2026 review, with barely a tenth at investment decision [IEA, Global Hydrogen Review 2026, October 2026]. 2027 tests the projects that survived the contraction.

The year the green premium is put to the test

2027 is the year the green premium stops being an argument and becomes a measurement. The question is no longer whether green hydrogen can be made, but whether it can be sold: at a price a buyer will pay, from a plant that has actually been built. On present evidence, the answer for most of the pipeline is not yet.

For half a dec­ade the sec­tor was priced on am­bi­tion, and in the year to Decem­ber 2025 the am­bi­tion it­self con­trac­ted. The In­ter­na­tional En­ergy Agency re­cords that the world’s an­nounced-for-2030 low-emis­sion hy­dro­gen pipeline fell from 49 to 37 mil­lion tonnes a year, and to 27 mil­lion tonnes in the 2026 re­view [IEA, Oc­to­ber 2026], the first such con­trac­tion on re­cord, with only about 9% of it hav­ing reached a final in­vest­ment de­cision [IEA, Dec 2025]. New off­take signed in 2024 fell to 1.7 Mtpa from 2.4 the year be­fore and stayed near 1.7 Mt in 2025, with only about a fifth backed by firm con­trac­tual com­mit­ments [IEA, Oc­to­ber 2026]. The mar­ket is fail­ing to con­vert de­mand, not build­ing it, and 2027 is the year that real­ity is meas­ured in tonnes rather than tar­gets.

A third fact has since over­taken both, and it is not a cost fact. Iran de­clared the Strait of Hor­muz closed within days of the United States and Is­raeli strikes of late Feb­ru­ary 2026, and flows through it re­main near zero [IMF PortWatch, via IFPRI, 18 Septem­ber 2026]. The Gulf's hy­dro­gen case is an ex­port case: it rests on ship­ping mo­lecules to Europe and to Asia through that water. In the first half of 2026 ni­tro­gen ex­ports fell 63% for Saudi Ar­a­bia, 37% for Qatar and 29% for the United Arab Emir­ates. Am­mo­nia is the car­rier the whole Gulf pipeline as­sumes, and the route it as­sumes is now the bind­ing con­straint, ahead of elec­tro­lyser cost and ahead of off­take. An ex­port pro­ject that can­not ship is not a pro­ject with a premium prob­lem; it is a pro­ject without a mar­ket. The reader should hold that against every Gulf volume in the pages that fol­low, in­clud­ing the blue volumes, which travel by the same sea.

Two facts frame the whole edi­tion. The first is that the green premium is not clos­ing: it is, on the cost side,

widen­ing. Green hy­dro­gen in Europe is priced at roughly $4.50 to $6.00 a kilo­gram against $1.50 to $2.50 for grey and $2.00 to $3.50 for blue, a premium of two to three times over blue and up to four times over grey [Green Fuel Journal, 2026]; CareEdge puts re­new­able hy­dro­gen at 1.5 to 5 times un­abated fossil, a wider band [CareEdge, 2026]. Elec­tro­lyser cap­ital cost, the input the en­tire thesis as­sumed would fall, rose by roughly 57% at the me­dian between 2022 and 2024. The second fact is that the two geo­graph­ies at­tack­ing this gap look noth­ing alike, and near-term the Gulf’s pro­du­cing volume is not even green.

The gap is not closing. Green hydrogen runs two to three times the cost of blue, and electrolyser capex rose ~57% in the two years the thesis assumed it would fall.

The Gulf is ex­port-led but blue-heavy in the near term. Its one bank­able green flag­ship (NEOM’s He­lios plant in Saudi Ar­a­bia) is sched­uled to reach first pro­duc­tion, but the re­gion’s 2026–27 volume lead­ers are blue-am­mo­nia plants: Qatar’s Am­mo­nia-7 and the UAE’s Ta’ziz. India is de­mand-led and do­mestic, its mar­ket man­u­fac­tured by auc­tion; but it had awar­ded roughly 862,000 tonnes a year of green-hy­dro­gen pro­duc­tion while com­mis­sion­ing only about 8,000 (some 0.16% of its 2030 tar­get) by early 2026 [Busi­ness Today, Jun 2026]. Both are bets on the same mo­lecule; both are, in the phys­ical world, earlier than the pipeline sug­gests.

This is not a bear­ish read so much as a lit­eral one. The dir­ec­tion is not in doubt: re­new­able power in the Gulf and in India is among the cheapest on earth (Abu Dhabi has con­trac­ted solar at $0.0135 a kilo­watt-hour, the cheapest elec­tri­city re­cor­ded any­where [PV Tech, 2020]), and Europe’s rule­book is cre­at­ing a class of buy­ers ob­liged to pay for the cer­ti­fied re­new­able mo­lecule. What is in doubt is the pace, and 2027 is the year the pace be­comes vis­ible: in first pro­duc­tion at NEOM, in the first blue car­goes from Qatar and Ruwais, in the first green am­mo­nia flow­ing into In­dian fer­til­iser plants, and in the first gov­ern­ment-back­stopped cargo land­ing at Rot­ter­dam.

The through-line

Read as a whole, the year re­solves into five move­ments, each de­veloped in Part III. The cost gap widens be­fore it nar­rows. The two mod­els (Gulf ex­port and In­dian de­mand) di­verge rather than con­verge, and the Gulf’s near-term out­put is blue. Off­take hardens as the

GCC & India HydrogenVolge Quarterly02 •

true bind­ing con­straint, the ref­er­ence bank­able struc­ture being a single cred­it­worthy buyer tak­ing the whole volume for the tenor of the debt. Europe’s re­new­able-fuel rules, backed from Janu­ary 2026 by the car­bon bor­der levy, be­come the de-facto pass­port for any mo­lecule seek­ing a premium buyer. And some­where on the map, at least one an­nounced pro­ject is delayed, de­scoped or shelved, the fable risk a con­tract­ing pipeline all but guar­an­tees.

The one-line read

The dir­ec­tion is settled; the pace has slipped. A pipeline that shrank for the first time, a premium that widened, and de­mand con­trac­ted rather than built: 2027 is the year the sec­tor is read in what ships, not what is an­nounced.

How this edition is sourced

Every fig­ure is at­trib­uted in­line and year-stamped, with numbered sources in the annex. Com­pany an­nounce­ments are treated as claims, not facts, and the status of each agree­ment (memor­andum or bind­ing take-or-pay con­tract) is stated where known, be­cause most head­line ex­port volumes across the Gulf and India are memor­anda, not con­tracts. A small num­ber of de­veloper fig­ures could not be in­de­pend­ently re­con­ciled (among them NEOM’s exact daily out­put and sev­eral In­dian cor­por­ate siz­ings) and are flagged where they ap­pear.

What fol­lows is the re­con­ciled basis, the two mod­els, the forces, and the Calls.

A contracting pipeline, and a widening premium

The reconciled basis for this edition, on one page. The headline is that the two numbers the thesis most needed to move in its favour (the announced pipeline and the electrolyser cost) moved against it in the year to December 2025.

  • 2030 pipeline, Dec 2025: 37 Mtpa, Down from 49 a year earlier, first-ever con­trac­tion [IEA, 2025]
  • Of pipeline at FID: ~9%, ~4.2 Mtpa op­er­a­tional or at FID by 2030 [IEA, 2025]
  • New off­take signed, 2024: 1.7 Mtpa, Down from 2.4 Mtpa in 2023 [IEA, 2025]
  • Elec­tro­lyser capex: +57%, Me­dian rise 2022–24, re­vers­ing the as­sumed de­cline [GFJ, 2026]
  • West vs China stack cost: ~4×, ~$2,500/kW West­ern vs ~$600/kW Chinese [GFJ, 2026]
  • Cheapest solar, /kWh: $0.0135, Abu Dhabi Al Dhafra: the Gulf’s real ad­vant­age [PV Tech, 2020]
  • India green-H₂ awar­ded: ~862,000 t/yr, 19 firms; only ~8,000 t/yr com­mis­sioned by Feb 2026 [BT, 2026]
  • India tar­get com­mis­sioned: ~0.16%, Of the 5-MTPA-by-2030 goal; ~1.3% of budget spent [BT, 2026]
  • Qatar Am­mo­nia-7 (blue): 1.2 Mtpa, Start-up 2026: the Gulf’s near-term volume is blue [MEES, 2024]

Re­con­ciled from the IEA Global Hy­dro­gen Re­view 2025, MNRE and SIGHT/SECI res­ults, Hy­drom and de­veloper dis­clos­ures, and cost work in Green Fuel Journal (2025–26). Ranges re­flect genu­ine source dis­agree­ment on scope and grade. Cur­rent to July 2026.

The one-line read

A pipeline that shrank, a premium that widened, and a de­mand mar­ket that con­trac­ted. The pro­jects that sur­vive 2027 are the ex­cep­tions, not the pipeline.

Green against grey and blue, per kilogram

The green premium is not a market failure to be argued away; it is an accounting fact, and in 2026 it is widening on the cost side. Green hydrogen runs two to three times the cost of blue and up to four times grey, and the electrolyser (the input assumed to cheapen) became more expensive.

The premium has three com­pon­ents, and the sec­tor’s hopes rest on only one of them mov­ing. The first is re­new­able power, the largest input and the Gulf’s and India’s strongest hand: Gulf solar is the cheapest elec­tri­city on earth and In­dian solar runs near $25–30 a mega­watt-hour, with pro­jec­ted cuts of around 40% in the lev­el­ised cost of hy­dro­gen into the early 2030s [GFJ, 2026]. The second is elec­tro­lyser cap­ital cost, which rose roughly 57% at the me­dian between 2022 and 2024, driven by input-cost in­fla­tion and de­mand for scarce West­ern man­u­fac­tur­ing ca­pa­city. The third is the cer­ti­fic­a­tion and lo­gist­ics of mov­ing a com­pli­ant mo­lecule to a dis­tant buyer.

PathwayCost, 2026Notes
Grey (natural gas)$1.50–2.50/kgThe unabated benchmark green must displace
Blue (gas + CCS)$2.00–3.50/kgThe Gulf’s near-term producing pathway
Green, Europe$4.50–6.00/kgRFNBO-grade; 2–3× blue, up to 4× grey
Green, India₹397–560/kg (~$4.70–6.65)Refining tenders IOC ₹397, BPCL/HPCL ₹387/kg
Green, China<$2/kgCheap alkaline stacks; not a Gulf/India cost

Cost bands, Green Fuel Journal 2026. Chinese elec­tro­lys­ers ~$600/kW against ~$2,500/kW in the West drive a pro­jec­ted 2030 bi­furc­a­tion: China and the Gulf at $2–3/kg, the West at $5–7/kg.

Against grey and blue, the green case there­fore rests not on cost but on ob­lig­a­tion: the ex­ist­ence of buy­ers

GCC & India HydrogenVolge Quarterly03 •
The green case does not rest on beating grey. It does not. It rests on buyers whose rules require the renewable molecule, and who will pay the premium to comply.

whose rules re­quire the re­new­able mo­lecule. That is the RFNBO pass­port, de­veloped in Part III, and it is the reason a widen­ing cost premium and a real mar­ket can co­ex­ist.

Awarded capacity against signed demand

The binding constraint of 2027 is not production capacity but contracted demand. New offtake signed across the whole global market fell to 1.7 Mtpa in 2024 and was flat in 2025, and the reference bankable structure (a single creditworthy buyer taking the entire volume for the life of the debt) exists in only a handful of projects.

Elec­tro­lyser sup­ply is being solved; India alone has awar­ded 3.0 GW of man­u­fac­tur­ing ca­pa­city across two tranches [SIGHT/SECI, 2024]. The ma­chine is not the scarce input. The scarce input is the buyer will­ing to sign a take-or-pay con­tract at a price that pays for the premium. Most of the head­line ex­port volumes quoted across the Gulf and India are memor­anda or frame­work agree­ments, not take-or-pay, and roughly 80% of com­mit­ted hy­dro­gen in­vest­ment world­wide still sits in ex­ist­ing in­dus­trial uses rather than new clean de­mand [IEA, 2025].

The contracts that actually bind

NEOM – Air Products. A 30-year ex­clus­ive off­take of 100% of He­lios out­put: the only struc­ture the Gulf has proven bank­able, and the an­chor that took the pro­ject to fin­an­cial close in May 2023 [5][6]. Fer­ti­globe – H2Global. The ADNOC/OCI ven­ture won Europe’s first im­port auc­tion at €1,000 a tonne into Rot­ter­dam: 19,500 tonnes in 2027 rising to 397,000 cu­mu­lat­ive by 2033, gov­ern­ment-back­stopped [5][29]. ACME – Japan. ACME’s Odisha am­mo­nia, with IHI, was cer­ti­fied for Japan’s con­tract-for-dif­fer­ence scheme in mid-2026, under a con­tract for dif­fer­ence cov­er­ing 228,000 tpa over 25 years from Septem­ber 2030, with com­mis­sion­ing ex­pec­ted July 2030 [30]. India fer­til­iser. SECI ag­greg­ated 724,000 t/yr of green-am­mo­nia de­mand; six agree­ments for 670,000 t/yr were signed on 31 March 2026 across 13 fer­til­iser units on ten-year terms [27].

Marked to verify

Where a large an­nounced ca­pa­city is paired with an un­named buyer or a non-bind­ing memor­andum, this edi­tion treats it as in­tent, not off­take. Read­ers should apply the same test: a tonne with no take-or-pay con­tract be­hind it does not fin­ance a plant.

The two models

The Gulf exports; India consumes. But the Gulf’s near-term volume is blue ammonia, not green (one bankable green flagship at NEOM against blue plants at Qatar and Ruwais), while India has auctioned a pipeline it has scarcely begun to build.

Saudi Arabia: NEOM, the one bankable green flagship

NEOM Green Hydrogen Company (the Helios plant at Oxagon) is the Gulf’s only bankable green flagship, and the exception that proves the rule about offtake. At roughly $8.4 billion it reached financial close in May 2023 on the strength of a single 30-year contract, and construction was reported complete to analysts on 6 August 2026, with commercial operations set for 2027 and Air Products guiding to first production in mid-2027 after what it calls a long commissioning process.

The pro­ject is an equal joint ven­ture of ACWA Power, Air Products and NEOM, and its struc­ture is the tem­plate the rest of the Gulf has not been able to rep­lic­ate: one very large plant, one deep con­sor­tium, and a single long-dated off­take that de-risked the whole. Air Products is the ex­clus­ive off­taker of 100% of the out­put for 30 years [Am­mo­nia En­ergy, 2023], and it was that con­tract, not the en­gin­eer­ing, that made fin­an­cial close pos­sible on 22 May 2023. The design pairs about 4 GW of solar and wind with more than 2 GW of thyssen­k­rupp elec­tro­lysis, con­vert­ing hy­dro­gen to am­mo­nia be­cause am­mo­nia, not hy­dro­gen, is what moves eco­nom­ic­ally across an ocean.

The 600 t/day hy­dro­gen fig­ure is car­ried from de­veloper dis­clos­ure and could not be in­de­pend­ently re­con­ciled; it is flagged as dir­ec­tional. First pro­duc­tion may slip from end-2026 into 2027.

The Call on NEOM is high-con­fid­ence but nar­row: first pro­duc­tion is a ramp ques­tion, not a de­mand one, be­cause 100% of the volume is already sold. What NEOM does not prove is re­peat­ab­il­ity: no second Gulf green megapro­ject has reached FID with bind­ing off­take, and that ab­sence, not NEOM’s pro­gress, is the re­gion’s real sig­nal.

GCC & India HydrogenVolge Quarterly04 •
AttributeDetailSource / status
ProjectNEOM Green Hydrogen Co. (Helios), OxagonJV ACWA Power / Air Products / NEOM, equal
Investment~$8.4 billionFinancial close 22 May 2023 [6][17]
Renewables~4 GW solar and wind[2][6]
Electrolysis>2 GW, thyssenkrupp[18]
Hydrogen output~600 t/day green H₂Developer disclosure: marked to verify
Ammonia output>1.2 Mtpa green ammonia[2][6]
OfftakeAir Products, exclusive, 100%, 30 yearsBinding [5]
StatusConstruction complete; first production mid-2027[7][8]

Oman: Hydrom, blocks auctioned ahead of demand

Oman has built the Gulf’s most orderly green-hydrogen programme, and exposed the sector’s defining flaw in doing so: supply is being auctioned ahead of demand. The blocks are allocated and the developers named; the binding buyers are not.

Oman’s dis­tinc­tion is Hy­drom, a state or­ches­trator that auc­tions defined land blocks at Duqm and Sala­lah under stand­ard terms rather than ne­go­ti­at­ing each pro­ject bi­lat­er­ally. Its second round in April 2024 al­loc­ated two Dho­far pro­jects at around $11 bil­lion of pro­spect­ive in­vest­ment, and a third round for Duqm was launched in May 2025 with awards due in 2026 [Hy­drom, 2024–25]. The na­tional am­bi­tion is roughly 1.38 Mtpa of hy­dro­gen by 2030, rising to­ward 7.5–8.5 Mtpa by 2050. The pipeline is un­usu­ally legible; its weak­ness is that the off­take to fill it has not been con­trac­ted.

ProjectDetailStatus
HyPort Duqm (OQ / Uniper / DEME)500 MW, ~60,000 t/yrPhase 1 ~2026
SalalaH2 (OQ / Linde)400 MW, ~$1bnFID targeted 2026
ACME Duqm3.5 GW RE → 900,000 t/yr ammonia; ~$3.5bnPhased; demand-side constrained
Dhofar R2 (EDF / J-POWER / Yamna; Actis / Fortescue)Two projects, ~$11bnRound 2, Apr 2024
GEO25 GW → up to 1.8 Mt H₂ / 10 Mt ammoniaLong-dated
Duqm Round 3Blocks launched May 2025Awards 2026

Hy­drom and de­veloper dis­clos­ures, 2024–25. ACME Duqm’s am­mo­nia ca­pa­city is auc­tioned; a bind­ing full-volume off­take had not been dis­closed as of mid-2026, the de­mand-side con­straint in mini­ature.

The Call on Oman is there­fore hedged to­ward the con­straint rather than the pipeline. Oman’s Round 3 Duqm awards were sched­uled for the second quarter

Oman auctioned the supply before the demand existed. The blocks are the easy part; the buyer for the tenor of the debt is the hard one.

of 2026 and none has been an­nounced, and no SalalaH2 FID is on re­cord: both are now over­due rather than pending. The re­gion’s green FIDs bey­ond NEOM re­main thin, and Oman’s legib­il­ity does not sub­sti­tute for the take-or-pay con­tracts that fin­ance plants.

UAE & Qatar: blue first, green offshored

The correction that most changes the Gulf story is this: the region’s near-term producing volume is blue ammonia, not green. The UAE’s Ta’ziz and Qatar’s Ammonia-7, both blue, are the plants scheduled to start up in 2026–27, while the UAE’s flagship green target has been pushed past 2030.

Ta’ziz closed $1.39bn of fin­an­cing on 4 Novem­ber 2026 and re­af­firmed 2027 op­er­a­tions. A ven­ture of ADNOC’s Fer­ti­globe with GS En­ergy and Mit­sui, it is build­ing 1.0 Mtpa of blue am­mo­nia at Ruwais (nat­ural gas re­formed with car­bon cap­ture), with con­struc­tion from the third quarter of 2024, first pro­duc­tion tar­geted in 2027, full car­bon cap­ture by 2030, and Mit­sui off­tak­ing into Japan and Asia [2][21]. Qatar’s Am­mo­nia-7, at Me­saieed, is 1.2 Mtpa of blue am­mo­nia with 1.5 Mtpa of CO₂ cap­ture, about $1.0–1.2 bil­lion, ground broken in Novem­ber 2024 and start-up in 2026 [MEES, 2024]. These are the Gulf’s real 2026–27 volumes, and they are blue.

ProjectTypeDetail / status
Ta’ziz (ADNOC/Fertiglobe + GS Energy + Mitsui)Blue ammonia1.0 Mtpa, Ruwais; construction Q3 2024; first production 2027; Mitsui offtake, Japan/Asia
Qatar Ammonia-7 (QatarEnergy/QAFCO)Blue ammonia1.2 Mtpa, Mesaieed; SMR + 1.5 Mtpa CCS; ~$1.0–1.2bn; start-up 2026
Masdar green (1 Mtpa)Green H₂Target pushed past 2030 (Oct 2024); migrated to European JVs (OMV, EnBW, TotalEnergies)
Helios Industry, KEZADGreen ammonia200,000 t/yr; pre-FID / stalled

Green Fuel Journal, MEES and Bloomberg, 2024–26. Mas­dar’s 1 Mtpa is de­scribed as “within the next dec­ade” and was ex­pli­citly delayed past 2030 in Oc­to­ber 2024. It should not be read as an on-track 2030 com­mit­ment.

The Gulf model, in one line

Ex­port-led, blue-heavy near-term, off­take-anchored. One bank­able green flag­ship (NEOM) against blue volume lead­ers (Qatar, Ta’ziz) and a delayed green tar­get (Mas­dar). The thesis’s green con­tent is thin­ner than the pipeline im­plies.

GCC & India HydrogenVolge Quarterly05 •

The Mission and SIGHT: awarded at scale, commissioned barely

India’s bet is the mirror image of the Gulf’s: a broad, publicly-funded programme that manufactures demand through auctions rather than backing a few export plants. Its defining number in 2026 is the gap between what has been awarded (roughly 862,000 tonnes a year of green hydrogen) and what has been commissioned: about 8,000 tonnes, some 0.16% of the 2030 target.

The Na­tional Green Hy­dro­gen Mis­sion, ap­proved on 4 Janu­ary 2023, car­ries an out­lay of ₹19,744 crore, a tar­get of at least 5 mil­lion tonnes a year of green hy­dro­gen by 2030, and about 125 GW of linked re­new­able ca­pa­city [MNRE, 2023]. Its in­stru­ment is SIGHT: ₹17,490 crore split between elec­tro­lyser man­u­fac­tur­ing (₹4,440 crore) and pro­duc­tion (~₹13,050 crore), with a pro­duc­tion in­cent­ive taper­ing ₹50 to ₹40 to ₹30 a kilo­gram over three years. The design is sound; the de­liv­ery is early. By 6 Au­gust 2026 roughly ₹292 crore, under 1.5% of the ₹19,744 crore out­lay, had been spent, and MNRE told Par­lia­ment that no elec­tro­lyser or pro­duc­tion fa­cil­ity sup­por­ted under SIGHT had been fully com­mis­sioned [MNRE, re­por­ted 3 Novem­ber 2026].

What SECI has awarded

AuctionVolumeDetail
Production, Mode-1 T-I (Jan 2024)~412,000 t/yrReliance 90,000 @ ₹18.90/kg (lowest); ACME & Greenko ZeroC 90,000 each @ ₹30/kg
Production, Mode-1 T-II (Mar 2025)450,000 t/yrOversubscribed 1.4×; AM Green/Waaree/Sembcorp/L&T 90,000 each; Reliance +49,000
Cumulative~862,000 t/yr19 firms; Reliance largest at ~139,000 t/yr
Electrolyser mfg3.0 GWT-I 1.5 GW (Jan 2024) + T-II 1.5 GW (Sep 2024); no T-III as of Jul 2026

SECI auc­tion res­ults, 2024–25. Re­li­ance’s ₹18.90/kg is the low­est pro­duc­tion bid; the pro­duc­tion in­cent­ive un­der­writes it. Awar­ded is not com­mis­sioned: the two dif­fer by more than a hun­dred­fold.

India awarded 862,000 tonnes a year of green hydrogen and commissioned about 8,000, some 0.16% of its 2030 target, on 1.3% of the budget.

The Call fol­lows dir­ectly: India com­mis­sions less than 5% of its 5-MTPA tar­get by end-2027. The pro­gramme is not fail­ing so much as it is early, and the dis­tance between an auc­tion award and a run­ning plant is the whole story of the In­dian year.

SECI/SIGHT auc­tion res­ults and de­veloper dis­clos­ures, 2024–26. Jam­nagar siz­ing, Adani’s ~1 Mtpa Mun­dra tar­get and AM Green’s wider pro­gramme are

de­veloper fig­ures partly pred­at­ing July 2026 and are flagged as dir­ec­tional. Awards are pro­duc­tion al­loc­a­tions, not com­mis­sioned ca­pa­city.

The Indian field: nineteen awardees, one table

The Indian programme is unusually broad (nineteen firms hold production awards), and that breadth is at once its resilience and its fragmentation risk. The table sets out the developers that matter, their awards and their standing.

DeveloperAward / projectScaleStatus
RelianceProduction + electrolyser mfg; Jamnagar~139,000 t/yr (largest) + 300 MW; ₹18.90/kg bidUnder build; “$1/kg by 2030” aspiration
Adani (ANIL)Mundra; electrolyser mfg~1 Mtpa target; 198.5 + 71.5 + 30 MWPhased
ACMEProduction + SECI green ammonia; Bikaner/TN/Oman90,000 t/yr + ~370,000 t/yr NH₃ (record ₹49.75/kg, IFFCO Paradeep)Awarded; Japan corridor via Odisha-IHI
L&TProduction + Hazira90,000 t/yr + 63 MWFirst indigenous electrolyser Mar 2024
NTPC / NGELGreen ammonia; Pudimadaka hub70,000 t/yr @ ₹51.80/kgPact signed 31 Mar 2026
Greenko / AM GreenKakinada90,000 t/yr production awardAwarded (T-II)
WaareeProduction + Valsad gigafactory90,000 t/yr + 300 MWAwarded
SembcorpProduction + Tuticorin90,000 t/yr; Kyushu Electric offtakeFirst output targeted 2029
OhmiumElectrolyser mfg; Bengaluru PEM274 MW; $250M Series C (TPG)Scaling
Jakson GreenGreen ammoniaRecord-low SECI ammonia bidAwarded
OthersHygenco, Welspun, Torrent, CESC, UPL, JSW, John Cockerill Greenko, Jindal, Advait, Matrix, AvaadaVariousAwarded / phased

The demand anchors: fertiliser, refining and steel

India’s answer to the offtake problem is to aggregate demand it can direct: its own fertiliser, refining and steel industries. The largest anchor is fertiliser, where 670,000 tonnes a year of green ammonia was contracted on 31 March 2026, India’s first at-scale green-hydrogen demand.

Through SECI, India ag­greg­ated 724,000 tonnes a year of green-am­mo­nia de­mand and signed six agree­ments for 670,000 tonnes across 13 fer­til­iser units on ten-year terms, at prices of ₹49.75 to ₹64.74 a kilo­gram against grey am­mo­nia at roughly ₹110, an

GCC & India HydrogenVolge Quarterly06 •

im­plied for­eign-ex­change sav­ing of about $2.5 bil­lion over the dec­ade [Mer­com, Mar 2026]. This is the de­mand that makes the In­dian model real: not a mer­chant ex­port hope but a do­mestic sub­sti­tu­tion of im­por­ted grey am­mo­nia, dir­ec­ted by the state into plants ob­liged to buy.

AnchorVolumeTerms / price
Fertiliser (SECI aggregated)724,000 t/yr670,000 t/yr signed with 11 units of the 13 allocated, 10 yrs
– price–₹49.75–64.74/kg vs grey ~₹110/kg; ~$2.5bn forex saving/decade
Refining (SIGHT)20,000 t/yr + 10,000IOC/BPCL/HPCL ₹387–397/kg; Numaligarh 10,000
SteelFirst cert Feb 2026Green Steel Taxonomy (<2.2 tCO₂e/t) notified 12 Dec 2024; ArcelorMittal Nippon Steel

Mer­com and MNRE, 2026. The fer­til­iser con­tracts are bind­ing ten-year off­take, the sub­stance be­hind the In­dian model. There is, how­ever, no eco­nomy-wide con­sump­tion ob­lig­a­tion as of mid-2026: de­mand is ag­greg­ated, not man­dated.

The Indian model, in one line

De­mand man­u­fac­tured by policy and anchored in fer­til­iser, re­fin­ing and steel. The strength is that off­take is con­trac­tual and do­mestic; the ex­pos­ure is that it is sub­sidy-de­pend­ent, un-man­dated, and, so far, barely built.

The Gulf con­cen­trates the bet and ships blue first; India spreads it and has scarcely begun. The cor­ridors and con­straints that fol­low bind both.

RFNBO, CBAM and the buyers in Europe and Asia

There are two export corridors, and they behave differently. Europe pulls the renewable molecule through a rulebook (RED III and, from January 2026, a carbon border levy), but pays only through government-backstopped auctions. Asia pulls ammonia as a co-firing fuel through contracts-for-difference. India’s binding export traction, notably, is Asia-facing, not European.

Europe is the gate­keeper. RED III, in force since Novem­ber 2023, re­quires 42% of in­dus­trial hy­dro­gen to be RFNBO by 2030 and 60% by 2035, sub­ject to Del­eg­ated Act tests on ad­di­tion­al­ity, tem­poral cor­rel­a­tion tight­en­ing to hourly from 1 Janu­ary 2030, and a li­fe­cycle green­house-gas sav­ing of at least 70% [EU, 2023]. REPowerEU tar­gets 20 Mt of re­new­able hy­dro­gen by 2030, split evenly between do­mestic pro­duc­tion and im­ports. But will­ing­ness to pay is thin: Europe’s first im­port auc­tion, run through H2Global, cleared green am­mo­nia at €1,000 a tonne, and it was won by Fer­ti­globe, a UAE-par­en­ted sup­plier, de­liv­er­ing 19,500 tonnes into Rot­ter­dam in 2027 [5][29].

IEA, EU, JOGMEC and Am­mo­nia En­ergy, 2024–26. Am­mo­nia is the car­rier of choice (li­quid at −33°C against −253°C for hy­dro­gen), and Japan’s JERA is run­ning a 20% co-fir­ing demon­stra­tion at its 1,000 MW Hek­inan sta­tion.

CorridorMechanism2027 signal
MENA/Gulf → RotterdamH2Global auction, €1,000/tFirst Fertiglobe cargo, 19,500 t, 2027
India → JapanJOGMEC CfD (¥3tn/15 yrs)ACME/IHI certified 2026; 228,000 tpa from Sep 2030
Gulf/Aus → KoreaCHPS co-firing auctionOnly KOSPO cleared (Dec 2024); ~11% of volume filled
EU rulebookRED III + CBAM (from 1 Jan 2026)42% RFNBO by 2030; carbon levy on H₂/ammonia

The cor­ridor con­clu­sion is un­com­fort­able for the green thesis: the bind­ing con­tracts that exist are either gov­ern­ment-back­stopped (H2Global, the Ja­pan­ese and Korean schemes) or single-buyer (NEOM). Mer­chant ex­port without a take-or-pay con­tract or a pub­lic back­stop is, in 2027, still a cor­ridor of in­tent.

Offtake, cost, power, water, financing

Seven constraints bind the sector, and they are ordered. Offtake is the master constraint; everything else is downstream of it. A plant with a binding buyer solves its financing; a plant without one cannot be built however cheap its power.

1 · Offtake (the master)

New off­take signed fell to 1.7 Mtpa in 2024 and was flat in 2025, and roughly 80% of com­mit­ted hy­dro­gen in­vest­ment world­wide re­mains in ex­ist­ing in­dus­trial uses rather than new clean de­mand [IEA, 2025]. Until take-or-pay con­tracts exist, the pipeline is a wish list.

2 · Cost and the premium

Green runs two to three times blue, and elec­tro­lyser capex rose about 57% between 2022 and 2024. West­ern stacks cost roughly four times Chinese ones, which de­cides who can build eco­nom­ic­ally and ex­poses Gulf and In­dian pro­jects to im­port policy.

3 · Power

Gulf and In­dian solar is the cheapest on earth, but round-the-clock firm­ing to keep elec­tro­lys­ers run­ning adds cost that re­cord day­time bids con­ceal.

4 · Water and desalination

Elec­tro­lysis needs ul­trapure water; in the Gulf that means de­sal­in­a­tion at scale, a cost and an en­ergy load, as NEOM’s in­teg­rated build shows.

5 · Infrastructure

Am­mo­nia ter­min­als, crack­ing ca­pa­city and ded­ic­ated ship­ping are nas­cent. The mo­lecule can be made be­fore it can be moved.

GCC & India HydrogenVolge Quarterly07 •

6 · The EU rulebook

RFNBO rules raise the bar for com­pli­ance and CBAM helps the green case at the mar­gin, but mer­chant European de­mand above the ~€1,000/t auc­tion clear­ing price is thin.

7 · India’s delivery gap

About 1.3% of the Mis­sion budget is spent, there is no bind­ing eco­nomy-wide con­sump­tion ob­lig­a­tion, and the grey-to-green switch de­pends on sub­sidy hold­ing.

The one-line read

Solve off­take and the rest be­comes en­gin­eer­ing. Leave it un­solved and cheap power, fall­ing-someday capex and a sup­port­ive rule­book do not build a single plant.

The forces shaping the year

Five through-lines cut across the two geographies. Each is a force that will move the sector in 2027, and together they explain the Calls that follow: the cost gap, the two models, the offtake bottleneck, the European passport, and the risk that a flagship does not ship.

Green or grey: the cost gap, and why it is widening

The green premium is widening on the cost side, and that is the fact from which the whole year follows. The input the thesis assumed would fall (the electrolyser) became more expensive, and the gap to grey and blue grew rather than shrank.

For a dec­ade the green case res­ted on a fall­ing cost curve: elec­tro­lys­ers would cheapen, re­new­able power was already cheap, and the two to­gether would close the gap to fossil hy­dro­gen. Half of that held. Re­new­able power is cheaper than ever: Gulf solar at little over a cent a kilo­watt-hour, In­dian solar near $25–30 a mega­watt-hour. But elec­tro­lyser cap­ital cost rose about 57% at the me­dian between 2022 and 2024 [GFJ, 2026], re­vers­ing the de­cline on which the arith­metic de­pended, as input-cost in­fla­tion and a scramble for scarce West­ern man­u­fac­tur­ing ca­pa­city over­whelmed the learn­ing curve.

The res­ult is a premium that, in 2026, runs two to three times blue and up to four times grey. And it frac­tures along a geo­pol­it­ical line. Chinese elec­tro­lys­ers cost roughly $600 a kilo­watt against about $2,500 in the West, a four-fold gap that in­creas­ingly de­cides who can build. The likely 2030 out­come is not con­ver­gence

but bi­furc­a­tion: China and the Gulf pro­du­cing at $2–3 a kilo­gram, the West at $5–7.

The curve the thesis was built on bent the wrong way. Cheap electrons were never the problem; the machine that splits the water is.

This is why the green case can­not rest on cost. Un­sub­sid­ised, green does not beat grey or blue in 2027, and the hon­est read­ing is that it will not for years. What green has in­stead is a set of buy­ers whose rules re­quire the re­new­able mo­lecule; and that reg­u­lat­ory de­mand, not a cost cros­sover, is what a green pro­ject must sell into. The cost gap is the reason the next three forces mat­ter as much as they do.

The world’s announced 2030 pipeline shrank for the first time: 49 to 37 million tonnes in a single year, and to 27 million tonnes in the 2026 review, and barely a tenth of it has reached an investment decision.

The state of the sec­tor · Volge Quarterly 2027

Two models of the same bet: export against demand

The Gulf and India are making the same bet on the same molecule in opposite ways, and 2027 tests both structures rather than settling which is right. The Gulf concentrates risk in a few export plants and ships blue first; India spreads risk across many developers and anchors demand at home.

The Gulf model is ex­port-led and cap­ital-con­cen­trated. It backs a small num­ber of very large plants against long-dated for­eign off­take, and its bank­able in­stance, NEOM, is de-risked by a single 30-year con­tract for 100% of out­put. The strength is bankab­il­ity; the ex­pos­ure is con­cen­tra­tion, and the awk­ward truth that the re­gion’s near-term pro­du­cing volume is blue am­mo­nia from Qatar and Ruwais, not green. The Gulf is de­car­bon­ising its ex­ist­ing am­mo­nia busi­ness faster than it is build­ing a green ex­port one.

The Gulf ships the molecule and starts with blue; India consumes it and has barely begun to build. Two bets on the same fuel, structured as opposites.

Neither model has been proven, and 2027 does not choose between them. What it does is ex­pose each to its own fail­ure mode: the Gulf to the thin­ness of green

GCC & India HydrogenVolge Quarterly08 •

FIDs bey­ond NEOM, India to the gulf between award and plant. The edi­tion backs both to sur­vive the year and neither to vin­dic­ate it­self in it.

The In­dian model is de­mand-led and cap­ital-dis­persed. It man­u­fac­tures de­mand through auc­tions, spreads pro­duc­tion awards across nine­teen firms, and an­chors off­take in its own fer­til­iser, re­fin­ing and steel in­dus­tries. The strength is that de­mand is con­trac­tual and do­mestic (670,000 tonnes a year of fer­til­iser off­take signed in March 2026) and im­mune to European will­ing­ness-to-pay. The ex­pos­ure is frag­ment­a­tion, fiscal de­pend­ence, and a com­mis­sion­ing re­cord of 0.16% of tar­get.

Offtake is the bottleneck: the binding constraint of 2027

Offtake, not electrolysers, is the binding constraint of 2027. The scarce input is not the machine that splits water but the signature of a creditworthy buyer willing to take the whole volume for the life of the debt.

The evid­ence is in the flows. New off­take signed across the global mar­ket fell to 1.7 Mtpa in 2024 from 2.4 the year be­fore and was flat in 2025: the mar­ket is fail­ing to con­vert de­mand, not build­ing it, and about 80% of com­mit­ted hy­dro­gen in­vest­ment still sits in ex­ist­ing in­dus­trial uses [IEA, 2025]. Mean­while elec­tro­lyser man­u­fac­tur­ing races ahead: India alone has awar­ded 3.0 GW. The asym­metry is the whole point. Sup­ply is being built faster than de­mand is being con­trac­ted, and a stack with no buyer is a stran­ded asset in wait­ing.

The ref­er­ence bank­able struc­ture is nar­row and worth stat­ing pre­cisely: a single cred­it­worthy buyer tak­ing 100% of out­put for the tenor of the debt. NEOM has it: Air Products, 30 years. Al­most noth­ing else does. The gov­ern­ment-back­stopped auc­tions (H2Global, Japan’s and Korea’s schemes) sub­sti­tute the state for the buyer, and India’s fer­til­iser con­tracts sub­sti­tute policy for the mar­ket. Every fin­anced pro­ject in the sec­tor traces to one of these three: a single buyer, a pub­lic back­stop, or a man­dated one.

Supply is auctioned; demand is contracted. The gap between the two is where the pipeline goes to die, and it is widening.

This is why the edi­tion reads the year in con­tracts rather than ca­pa­city. A memor­andum is a hope; a take-or-pay con­tract is a plant. The pro­jects that reach first pro­duc­tion in 2027 will, without ex­cep­tion, have solved off­take first.

NEOM’s $8.4 billion plant sells 100% of its output to one buyer for thirty years. It is the only structure the Gulf has proven bankable, and almost nothing else has it.

The forces · Volge Quarterly 2027

The RFNBO passport: Europe’s rulebook as the gate

Europe’s renewable-fuel rulebook is becoming the de-facto passport for any molecule seeking a premium buyer. Compliance with RED III’s RFNBO definition, reinforced from January 2026 by the carbon border levy, increasingly decides which projects can access European demand at all.

RED III, in force since Novem­ber 2023, re­quires 42% of in­dus­trial hy­dro­gen to be RFNBO by 2030 and 60% by 2035. The Del­eg­ated Acts set the tests that make cer­ti­fic­a­tion hard: ad­di­tion­al­ity (new re­new­able ca­pa­city, with elec­tro­lys­ers com­mis­sioned be­fore 2028 grand­fathered until 2038); tem­poral cor­rel­a­tion tight­en­ing from monthly to hourly match­ing from Janu­ary 2030; and a li­fe­cycle green­house-gas sav­ing of at least 70% [EU, 2023]. From 1 Janu­ary 2026 the car­bon bor­der ad­just­ment mech­an­ism began its defin­it­ive re­gime, reach­ing hy­dro­gen and am­mo­nia through fer­til­isers, tilt­ing the landed eco­nom­ics to­ward the com­pli­ant mo­lecule.

The pass­port cuts two ways. It is the reason a green pro­ject can com­mand a premium at all: the rules man­u­fac­ture buy­ers ob­liged to pay. But it is also a gate: a non-com­pli­ant mo­lecule, how­ever cheap, is locked out of the European mar­ket, and cer­ti­fic­a­tion is neither quick nor cer­tain. AM Green’s pre-cer­ti­fic­a­tion and ACME’s Ja­pan­ese cer­ti­fic­a­tion are com­pet­it­ive as­sets pre­cisely be­cause they are scarce.

Europe does not subsidise the molecule; it obliges someone to buy it. The rulebook is the demand, and compliance is the ticket to it.

The Call is that RFNBO com­pli­ance forces at least one an­nounced Gulf or In­dian EU-ex­port memor­andum to lapse or re­struc­ture by end-2027, the gate clos­ing on a pro­ject that as­sumed ac­cess it had not earned.

The edi­tion names fable risk as a force rather than a pre­dic­tion be­cause its pre­cise loc­a­tion is un­know­able and its oc­cur­rence is near-cer­tain. Some an­nounced pro­ject (in the Gulf or in India) that today car­ries a con­fid­ent timeline will, by end-2027, carry a slipped one

GCC & India HydrogenVolge Quarterly09 •

or none at all. The dis­cip­line is to hold every an­nounced fig­ure to the ques­tion the whole edi­tion asks: is there a bind­ing buyer be­hind it, and has ground ac­tu­ally been broken?

Fable risk: the project that does not ship

A pipeline that shrank for the first time all but guarantees that at least one announced flagship is delayed, descoped or shelved in 2027. The question is not whether fable risk is realised but where.

The IEA’s con­trac­tion, 49 to 37 Mtpa of an­nounced 2030 ca­pa­city in a single year and 27 Mt by the 2026 re­view, is fable risk meas­ured in ag­greg­ate: pro­jects that ex­is­ted on paper and then did not. At the in­di­vidual level the same force op­er­ates. Mas­dar’s 1 Mtpa green tar­get was pushed past 2030 in Oc­to­ber 2024 and its green am­bi­tion mi­grated into European joint ven­tures. The KEZAD green-am­mo­nia pro­ject sits pre-FID and stalled. Adani’s TotalEnergies part­ner­ship was paused after 2023. None of these is a scan­dal; each is the or­din­ary at­tri­tion of a young, ex­pens­ive sec­tor meet­ing the cost of cap­ital.

In a pipeline that shrank for the first time, the safest prediction is subtraction: somewhere, a flagship that will not ship.

The five forces con­verge on a single in­struc­tion for the reader: count tonnes and con­tracts, dis­count an­nounce­ments, and ex­pect the map to lose a pro­ject be­fore it gains one. The Calls apply that dis­cip­line to the year.

Begin with what is pro­du­cing, be­cause the list is short and en­tirely In­dian. It com­prises demon­stra­tion as­sets: ACME's Bik­aner plant, Hy­genco's Hisar fa­cil­ity serving Jin­dal Stain­less, a 1 MW unit com­mis­sioned at Kandla Port in July 2025 (In­dian In­fra­struc­ture, 7 May 2026), and an NTPC sta­tion at Leh with five fuel-cell buses. Com­mis­sioned In­dian ca­pa­city is given as about 8,000 tpa of hy­dro­gen as at Feb­ru­ary 2026 (Busi­ness Stand­ard, 3 Novem­ber 2026), while a tracker gives 14,720 tpa of hy­dro­gen and 1,750 tpa of am­mo­nia as at May 2026 (India In­fra­struc­ture Re­search, July 2026). The two are un­re­con­ciled and both are set out for that reason. In the GCC no pro­du­cing green hy­dro­gen asset was found at all.

The com­mis­sion­ing cat­egory con­tains the two as­sets on which Gulf cred­ib­il­ity now rests. NEOM Green Hy­dro­gen Com­pany at Oxagon, held in thirds by ACWA Power, Air Products and NEOM, com­prises 2.2 GW of thyssen­k­rupp Nu­cera al­kaline elec­tro­lysis, 600 t/day of hy­dro­gen, about 1.2 Mtpa of green am­mo­nia and 4 GW of wind and solar, at USD 8.4bn as at fin­an­cial close in May 2023. Con­struc­tion was re­por­ted

com­plete and the plant in com­mis­sion­ing in Au­gust 2026, with com­mer­cial op­er­a­tion tar­geted in 2027 (TradeArabia, 25 Au­gust 2026, cit­ing ACWA). That is a slip, and it should be re­cor­ded as one: Air Products had filed on-stream in 2026 in its Form 10-K for FY2023 (SEC). No cost over­run has been re­por­ted.

The buyer's ground

The pipeline sorted by what is actually true, the short list of binding offtake, the only prices anyone has published, and who is in fact obliged to buy.

The pipeline, sorted by what is actually true

Almost nothing in the GCC or India is producing. The status word attached to a project carries more commercial information than its capacity figure, and nearly all the headline capacity sits in the weakest status of all.

What the pipeline shows is that al­most noth­ing in the GCC or India is pro­du­cing hy­dro­gen or am­mo­nia at scale, and that the status word at­tached to a pro­ject tells a buyer far more than its ca­pa­city fig­ure does. The table below sorts the two re­gions into the only five cat­egor­ies that carry com­mer­cial mean­ing: pro­du­cing, com­mis­sion­ing, under con­struc­tion, FID taken, and an­nounced only. Nearly all the ca­pa­city routinely quoted sits in the last of them. It is to be noted that a fig­ure in the an­nounced column is a state­ment of a de­veloper's in­ten­tion, car­ry­ing no date on which an off­taker or an equity sub­scriber could rely.

ProjectLocationScale as statedStatus as at November 2026Source and date
ACME Bikaner demonstration plantIndiaDemonstration scale, capacity not statedProducingPIB, 2021
Hygenco HisarIndiaSupply to Jindal StainlessProducingDeveloper material
Kandla Port unitIndia1 MWProducing, commissioned July 2025Indian Infrastructure, 7 May 2026
NTPC Leh stationIndiaStation and five fuel-cell busesProducingScheme record
NEOM Green Hydrogen Company, OxagonSaudi Arabia2.2 GW alkaline, 600 t/day hydrogen, about 1.2 Mtpa green ammoniaCommissioning complete August 2026, commercial operation targeted 2027TradeArabia, 25 Aug 2026, citing ACWA
QAFCO 7, MesaieedQatar1.2 Mtpa blue ammonia, about 1.5 Mtpa carbon captureConstruction from Nov 2024, Q2 2026 start reaffirmed, start-up not publicQatarEnergy and QAFCO, 31 Aug 2022; QCIntel
GCC & India HydrogenVolge Quarterly10 •

Four pro­jects are genu­inely under con­struc­tion. TA'ZIZ Ruwais, 1.0 Mtpa of blue am­mo­nia held by TA'ZIZ, Fer­ti­globe, Mit­sui and GS En­ergy, reached fin­an­cial close on USD 1.39bn for two Ruwais pro­jects on 4 Novem­ber 2026, over USD 460m of it for the am­mo­nia plant (The Na­tional, 4 Novem­ber 2026). The am­mo­nia EPC, with Tec­n­i­mont, is over 90 per cent com­plete and first pro­duc­tion is put at 2027 by Fer­ti­globe's chief ex­ec­ut­ive (Zawya, around 9 Novem­ber 2026). No bind­ing third-party off­take has been pub­lished. ACME Duqm phase 1 is past 50 per cent com­plete with elec­tro­lys­ers ordered and first mo­lecule in Q1 2027, at a cap­ital value that is not pub­lic (ACME via Oman Ob­server, 15 Decem­ber 2025).

ProjectLocationScale as statedStatus as at November 2026Source and date
TA'ZIZ Ruwais low-carbon ammoniaUAE1.0 Mtpa blue ammoniaUnder construction, ammonia EPC over 90 per cent complete, first production 2027Zawya, c. 9 Nov 2026
ACME Duqm phase 1Oman100,000 tpa green ammoniaUnder construction, past 50 per cent, first molecule Q1 2027ACME via Oman Observer, 15 Dec 2025
AM Green KakinadaIndia1 Mtpa ammonia in two trains, 1.3 GW alkalineUnder construction, FID end-August 2024, first major erection 17 Jan 2026AM Green via Ammonia Energy, Feb 2026
Hygenco GopalpurIndiaInitial phase, capacity not statedUnder construction, initial phase targeted December 2026Developer material
Indian Oil PanipatIndia10,000 tpa hydrogen, 25-year build-own-operate supplyFID taken, early works; commissioning conflicted between Dec 2026 and Dec 2027L&T exchange filing, 21 Jul 2025
ACWA Power YanbuSaudi ArabiaAbout 2.5 Mtpa green ammonia on ACWA's own materialAnnounced only, FEED awarded July 2025, no FID, operation targeted 2030ACWA; AGBI, Feb 2026
SABIC Agri-Nutrients JubailSaudi Arabia1.2 Mtpa blue ammonia after a gas allocation resetAnnounced only, FID and EPC still to comeExchange filing, 26 Mar 2026
ProjectLocationScale as statedStatus as at November 2026Source and date
Hydrom awarded blocks: Amnah, Green Energy Oman, Hyport Duqm, SalalaH2, EDF and J-POWER and Yamna, Actis and FortescueOmanAbout 200 ktpa, 150 ktpa, over 50 ktpa by 2029, over 1 Mtpa ammonia, about 178 ktpa; one not statedAnnounced only, all pre-FID; first FID expected 2026 or 2027Hydrom, accessed 10 Nov 2026; MEES, 7 Mar 2025
NTPC PudimadakaIndia7 GW renewables, about 1,400 tpd hydrogenAnnounced only, jetty detailed-project-report tendering, no FIDRenewable Watch, 25 May 2026
Adani MundraIndia1 Mmtpa phase 1Announced only; sole commissioned asset is a 5 MW off-grid pilot at KutchAEL intimation, 23 Jun 2025; T&D India, 2026
Reliance Jamnagar electrolyser gigafactoryIndiaCapacity not statedAnnounced only, operational by end-2026 claimed, no 2026 updateReliance AGM, Aug 2025

Ca­pa­cit­ies, cap­ital val­ues and dates in the an­nounced rows trace to de­veloper ma­ter­ial or press re­leases, not to fil­ings or awards. NEOM's USD 8.4bn, NTPC Pudimadaka's Rs 1.85 lakh crore and Re­li­ance's 3 Mtpa by 2032 are all of that char­ac­ter.

Qatar's QAFCO 7 at Me­saieed is the blue equi­val­ent: 1.2 Mtpa with about 1.5 Mtpa of car­bon cap­ture, an EPC of about USD 1bn, FID in 2022, con­struc­tion from Novem­ber 2024 and a Q2 2026 start re­af­firmed in May 2025 (QatarEnergy and QAFCO, 31 Au­gust 2022; QCIntel). Ac­tual start-up is not pub­lic, and in Novem­ber 2026 that si­lence is it­self the find­ing. QatarEnergy is the sole off­taker, an intra-group ar­range­ment rather than third-party off­take, so the pro­ject proves en­gin­eer­ing rather than de­mand.

A capacity figure in the announced column is an intention; the status word is the only part of the entry on which a buyer can rely.

The announced column, and the scheme that governs India

AM Green Kak­in­ada car­ries the only pub­lished FID date in the en­tire In­dian pipeline, taken at the end of Au­gust 2024, for 1 Mtpa of am­mo­nia on 1.3 GW of John Cock­er­ill al­kaline ca­pa­city, with CertifHy RFNBO pre-cer­ti­fic­a­tion and first major equip­ment erec­tion on 17 Janu­ary 2026. First sup­ply has non­ethe­less slipped from the second half of 2026 to 2028 on AM Green's own ma­ter­ial. In­dian Oil Pan­ipat sits one rung lower, at

GCC & India HydrogenVolge Quarterly11 •

FID with early works: 10,000 tpa of hy­dro­gen on a 25-year sup­ply awar­ded to L&T En­ergy GreenTech on 21 July 2025, with com­mis­sion­ing dates that con­flict between Decem­ber 2026 and Decem­ber 2027.

The an­nounced column is where the large num­bers live. ACWA Power Yanbu, at about 2.5 Mtpa of green am­mo­nia on ACWA's own ma­ter­ial, has FEED awar­ded in July 2025 and a 2030 op­er­a­tion tar­get, but neither cap­ital value nor elec­tro­lyser ca­pa­city is pub­lic. SABIC Agri-Nu­tri­ents Jubail, reset to 1.2 Mtpa of blue am­mo­nia on a gas al­loc­a­tion change with FID and EPC still to come (ex­change fil­ing, 26 March 2026), is the best-sourced Saudi blue data­point avail­able. Oman's awar­ded blocks are all pre-FID, with equity splits and cap­ital val­ues un­dis­closed in every case.

India's an­nounced tier re­quires the same scep­ti­cism. Adani Mun­dra claims 1 Mmtpa in phase 1, yet its only com­mis­sioned asset is a 5 MW pilot at Kutch and MNRE has stated there is no vis­ib­il­ity of pro­jects in the Mun­dra re­gion.

One scheme-level fact gov­erns the whole In­dian column. MNRE told Par­lia­ment that as at July 2026 no elec­tro­lyser man­u­fac­tur­ing fa­cil­ity and no green hy­dro­gen pro­duc­tion fa­cil­ity sup­por­ted under SIGHT had been fully com­mis­sioned, so no in­cent­ive had been claimed or paid, and that Rs 292 crore of the Rs 19,744 crore mis­sion out­lay had been spent by Au­gust 2026, under 1.5 per cent (Busi­ness Stand­ard, 12 Au­gust and 3 Novem­ber 2026). The same reply gives awar­ded totals of 3,000 MW per year of elec­tro­lyser man­u­fac­tur­ing to 15 com­pan­ies and 756,100 tpa of hy­dro­gen pro­duc­tion to 16 com­pan­ies, the lat­ter con­flict­ing with the 862,000 tpa cir­cu­lated in 2025 re­port­ing.

The 756,100 tpa and 862,000 tpa In­dian awar­ded totals could not be re­con­ciled from any primary source. Both are re­por­ted here without pref­er­ence.

The takeaway for any­one sign­ing an off­take agree­ment or an equity cheque is a pro­ced­ural one: the ca­pa­city num­ber in a de­veloper's deck is the least load-bear­ing item in it. The status word, the pub­lished FID date, the EPC com­ple­tion per­cent­age and the iden­tity of the off­taker are the load-bear­ing items, and in both re­gions those four fields are empty more often than filled. A pipeline in which one In­dian pro­ject has a pub­lished FID date, and no Gulf green asset is yet pro­du­cing, is a set of op­tions rather than a sup­ply curve.

Take the bind­ing Gulf-ori­gin agree­ments first, be­cause there are only two. Air Products takes all NEOM am­mo­nia for 30 years on an ex­clus­ive basis, de­scribed in its SEC fil­ings as fixed-price with the fig­ure with­held. A down­stream mar­ket­ing agree­ment with Yara, fi­nal­ised in 2026 and paid on com­mis­sion, cov­ers volumes Air Products does not it­self re­con­vert (Air Products 8-K, FY2026). Second, ACME Duqm has a bind­ing 15-year

agree­ment with Yara Clean Am­mo­nia for 100,000 tpa, the en­tire phase 1 out­put, RFNBO-com­pli­ant and sup­plied from 2027, at a price not pub­lic. That is the com­plete list, and no bind­ing GCC-ori­gin off­take with any Ja­pan­ese or Korean buyer ex­ists on the pub­lic re­cord.

Offtake, the binding constraint, proved by name

Offtake, not capacity and not cost, is what the sector is short of. The list of binding agreements is short enough to be printed in full, and the public record of retreats names the constraint explicitly.

The con­straint on this sec­tor is off­take, and the po­s­i­tion can be proved by name rather than as­ser­ted. The com­plete list of bind­ing GCC-ori­gin green off­take found runs to two agree­ments. The list of bind­ing India-ori­gin agree­ments is longer but still count­able on two hands. Against that sits a much longer list of memor­anda, let­ters of in­tent and single car­goes that are routinely re­por­ted as off­take and are not. Most sig­ni­fic­ant of all, the re­treats are ex­pli­cit: Ara­mco cut its 2030 blue am­mo­nia tar­get from 11 Mtpa to about 2.5 Mtpa ex­pressly for want of long-term off­take (En­ergy In­tel­li­gence, March 2025). Ex­actly one Gulf green am­mo­nia pro­ject is build­ing against a signed bind­ing off­take, and it is In­dian-owned.

BuyerSeller or originVolumeTenorPriceLegal character
Air ProductsNEOM Green Hydrogen Company, Saudi ArabiaAll ammonia produced30 years, exclusiveFixed price, figure withheldBinding
Yara Clean AmmoniaACME Duqm, Oman100,000 tpa, the entire phase 1 output, RFNBO-compliant15 years, from 2027Not publicBinding
Yara, as marketerAir Products, for NEOM volumes not reconvertedNot disclosedNot disclosedCommission basis, no rate disclosedBinding, finalised 2026
Thirteen Indian fertiliser plants, via SECIIndian producers724,000 tpa awarded, 670,000 tpa across 11 plants signed March 202610 years, fixed priceRs 49.75 to 64.74 per kgBinding where signed; two plants unsigned
UniperAM Green, IndiaUp to 500,000 tpa RFNBO ammonia from 2028Long-term, tenor not publicNot publicBinding, announced January 2026
JERAAM Green, India70,000 tpaFive yearsNot publicBinding head of agreement
GCC & India HydrogenVolge Quarterly12 •
BuyerSeller or originVolumeTenorPriceLegal character
HintcoAM Green phase 2, IndiaMinimum EUR 585m of ammonia over the term10 years from 2029Per-tonne price withheldBinding, awarded 30 September 2026
IHIACME, India405,000 tpa for JapanLong-term, tenor not publicNot publicBinding, reported July 2026
Mitsubishi Gas ChemicalACME Paradip, India100,000 tpa green methanol10 yearsNot publicBinding
EnBW, VNG and Rostock PortACWA PowerNo volume statedNoneNoneMemorandum, 1 February 2026
OMVMasdarNot statedNoneNoneLetter of intent, 30 April 2025
YaraGreenko ZeroCNot statedNoneNoneNon-binding
RWE, BASF and KeppelAM GreenNot statedNoneNoneNon-binding
MitsuiADNOC and FertiglobeOne certified bulk commercial cargoNoneNot publicCargo, not term offtake
Japanese buyer, 2020Aramco40 t demonstration cargoNoneNot publicDemonstration
South Korean buyer, 2022AramcoAbout 25,000 tNoneNot publicSpot, no term offtake

The India-ori­gin list is longer and more com­mer­cially con­vin­cing, in part be­cause its an­chor is a state pro­cure­ment. SECI's SIGHT Mode 2A Tranche I awar­ded 724,000 tpa across 13 fer­til­iser plants on 10-year fixed-price agree­ments with SECI as in­ter­me­di­ary pro­curer, and agree­ments for 670,000 tpa across 11 plants were signed in March 2026, which leaves two un­signed (SECI; Busi­ness Stand­ard, 3 Novem­ber 2026). AM Green has a bind­ing agree­ment with Uni­per for up to 500,000 tpa of RFNBO am­mo­nia from 2028, an­nounced in Janu­ary 2026, su­per­sed­ing a non-bind­ing 250,000 tpa ar­range­ment of 2023; a bind­ing head of agree­ment with JERA for 70,000 tpa over five years; and the sole win­ning bid in H2Global's round two Asian lot, under which Hintco will buy a min­imum of EUR 585m of am­mo­nia over ten years from 2029.

Exactly one Gulf green ammonia project is building against a signed binding offtake, and it is Indian-owned.

ACME holds a long-term bind­ing agree­ment with IHI for 405,000 tpa of India-ori­gin am­mo­nia destined for Japan, sup­por­ted by METI's con­tract for dif­fer­ence and re­por­ted in July 2026, and a ten-year agree­ment with Mit­subishi Gas Chem­ical for 100,000 tpa of green meth­anol from Paradip. MNRE re­ports ag­greg­ate firm off­take of about 555,610 tpa as at Oc­to­ber 2026 (Busi­ness Stand­ard, 29 Oc­to­ber 2026), though fig­ures vary between re­ports. It is to be noted that the ten­ors of the ACME and Yara Duqm, ACME and IHI, and AM Green and Uni­per agree­ments are stated only as long-term, and that no con­tract price among them is pub­lic.

The longer list, and what it actually is

Against that short list sits the much longer list of in­stru­ments that carry the word off­take in re­port­ing and none of its ob­lig­a­tions. ACWA Power's ar­range­ment with EnBW, VNG and Rostock Port, dated 1 Feb­ru­ary 2026, is a memor­andum with no volume and no price (EnBW). Hy­drom's ar­range­ments with H2Global and with VNG are memor­anda. The Oman to Neth­er­lands to Ger­many li­quid hy­dro­gen cor­ridor of April 2025 is a joint de­vel­op­ment agree­ment for in­fra­struc­ture between el­even parties, not an off­take at all. Mas­dar and OMV signed a let­ter of in­tent on 30 April 2025. Greenko ZeroC with Yara, and AM Green with RWE, BASF and Kep­pel, are de­scribed as non-bind­ing by S&P Global. Ara­mco has no term off­take of any kind: only a 40 t demon­stra­tion cargo to Japan in 2020 and about 25,000 t to South Korea in 2022.

One fre­quently cited item de­serves sep­ar­at­ing out. ADNOC and Fer­ti­globe's May 2024 ar­range­ment with Mit­sui is a cer­ti­fied bulk com­mer­cial cargo, not a term agree­ment, and Mit­sui is sim­ul­tan­eously an equity part­ner in TA'ZIZ. Volume, tenor and price are not pub­lic. A cargo sold to a party that also owns part of the plant says very little about the price at which in­de­pend­ent de­mand can be found.

Con­trac­ted ton­nage for Yara under the NEOM mar­ket­ing agree­ment and for Mit­sui under TA'ZIZ is not pub­lic. TA'ZIZ equity per­cent­ages and any bind­ing third-party am­mo­nia off­take for that plant could not be sourced.

The re­treats are where the con­straint is named rather than in­ferred. Ara­mco's re­duc­tion of its 2030 blue am­mo­nia tar­get from 11 Mtpa to about 2.5 Mtpa was at­trib­uted ex­pli­citly to the ab­sence of long-term off­take (En­ergy In­tel­li­gence, March 2025). ADNOC and Fer­ti­globe re­phased Pro­ject Rab­dan and aban­doned an early-2026 FID on weak buyer in­terest (En­ergy In­tel­li­gence and QCIntel, 2026). Two of Oman's nine awar­ded blocks were ter­min­ated by mu­tual agree­ment in late 2025 (Hy­drom, 8 Decem­ber 2025): BP ex­ited Duqm, a 1.5 GW po­s­i­tion, and HyDuqm, re­por­ted at

GCC & India HydrogenVolge Quarterly13 •

USD 6.7bn, was con­cluded on the same date. None of these is a tech­nical fail­ure: each is a de­mand fail­ure, stated as such by the parties.

The de­mand side has also been los­ing sinks faster than it has been adding them. Mas­dar scrapped the 100 MW Em­steel elec­tro­lyser after bids had been re­ceived, on 1 Au­gust 2026, and re­dir­ec­ted 6 GW of solar ear­marked for a 350,000 tpa am­mo­nia pro­ject to data centres (MEED and En­ter­prise, Au­gust 2026). ArcelorMittal can­celled hy­dro­gen dir­ect-re­duced iron at Bre­men and Eis­en­huetten­stadt in June 2025, re­vok­ing a claim to about EUR 1.3bn of Ger­man sub­sidy and re­mov­ing a de­mand sink in the pro­cess. Yara shelved green con­ver­sion at Pors­grunn and Slu­iskil, to­gether 530,000 tpa, in Oc­to­ber 2024. Korea's second CHPS auc­tion was can­celled on the bid dead­line day it­self, 17 Oc­to­ber 2025, and SECI scrapped its two hub pro­pos­als in July 2025.

The takeaway is that the sup­ply ques­tion in both re­gions has been answered and the de­mand ques­tion has not. A buyer eval­u­at­ing a pro­ject should there­fore treat the iden­tity and legal char­ac­ter of the ex­ist­ing off­take as the first di­li­gence item, ahead of ca­pa­city, cost and tech­no­logy. Where the an­swer is a memor­andum, a let­ter of in­tent, a single cargo or an intra-group sale, the pro­ject has not yet demon­strated that any­one will pay for its out­put, and on the pub­lished re­cord that de­scrip­tion fits the over­whelm­ing ma­jor­ity of an­nounced ca­pa­city in both re­gions.

The only prices anyone has published

Three price series exist in or adjacent to these two regions, and all three are Indian or European. Every GCC-origin contract price is undisclosed, without exception.

The po­s­i­tion on price is that India's SECI auc­tion is the only dis­covered green am­mo­nia price series in either re­gion, that H2Global's pilot auc­tion is the only pub­lished green am­mo­nia clear­ing price out­side India, that In­dian re­finery hy­dro­gen has two con­flict­ing pub­lished prints, and that every GCC-ori­gin con­tract price is un­dis­closed without ex­cep­tion. That last sen­tence is not an omis­sion in the re­search. It is the find­ing. A buyer can­not bench­mark a Gulf cargo against any pub­lished Gulf con­tract, be­cause none has been pub­lished, in­clud­ing the Air Products and NEOM agree­ment, which fil­ings con­firm is fixed-price while with­hold­ing the fig­ure.

Two fea­tures of that res­ult mat­ter more to a buyer than the head­line av­er­age. The first is the spread. A band from Rs 49.75 to Rs 64.74 per kg, on the same product under the same scheme in the same tranche,

Award or auctionDateVolumePrice as publishedTenor
SECI SIGHT Mode 2A Tranche I, weighted average2025724,000 tpa awarded across 13 plantsRs 53.27 per kg, about USD 604 per t, delivered10 years, fixed
SECI Mode 2A, lowest lot: ACME to IFFCO Paradeep2025100,000 tpaRs 49.75 per kg10 years, fixed
SECI Mode 2A, highest lot: ACME to Indorama Haldia202520,000 tpaRs 64.74 per kg10 years, fixed
H2Global pilot auction: Hintco to Fertiglobe, Egypt origin2024Minimum 40,000 tpaEUR 811 per t ex-factory, EUR 1,000 per t delivered EuropeDeliveries 2028 to 2033
H2Global round two, Asian lot: Hintco to AM Green phase 230 September 2026Minimum EUR 585m of ammonia over the termPer-tonne price withheld pending publication of all lots10 years from 2029
Indian Oil refinery hydrogen auctionReported via IEEFA, June 2025Volume not statedRs 397 per kg, about USD 4.67 per kg25 years
Lowest reported Indian refinery hydrogen printBusiness Standard, 3 November 2026Volume not statedRs 279 per kgNot stated
Indian refinery awards as tabulated by the IEAGlobal Hydrogen Review 2025Volume not statedNear Rs 328 per kg, about USD 3.8 per kgNot stated
Every GCC-origin contract, including Air Products and NEOMTo November 2026Includes all NEOM ammoniaUndisclosed; filings confirm fixed price without giving it30 years for NEOM

is about 30 per cent, and it tracks lot size: the cheapest lot is five times the volume of the dearest. Scale and the iden­tity of the re­ceiv­ing plant are there­fore doing sig­ni­fic­ant work in the price. The second is con­cen­tra­tion. ACME holds six of the 13 lots and 370,000 tpa of the award, slightly more than half. A series in which one sup­plier holds half the volume is a real price, but a price dis­covered in a thin mar­ket.

The second series is European and sits one step re­moved. H2Global's pilot auc­tion, run in 2024, saw Hintco con­tract Egyp­tian-ori­gin am­mo­nia from Fer­ti­globe at EUR 811 per t ex-fact­ory and EUR 1,000 per t de­livered into Europe, for a min­imum of 40,000 tpa with de­liv­er­ies from 2028 to 2033, against a sub­sidy of about EUR 397m (Hintco; Veyt). This re­mains the only pub­lished green am­mo­nia auc­tion clear­ing price out­side India. Its mech­an­ism mat­ters: Hintco buys high and re­sells at whatever the mar­ket will bear, with the

GCC & India HydrogenVolge Quarterly14 •

pub­lic purse ab­sorb­ing the dif­fer­ence, so EUR 1,000 per t is the price at which sup­ply could be se­cured, not the price at which de­mand was found.

The SECI auc­tion is the centrepiece be­cause it is the only place where com­pet­it­ive bid­ding has pro­duced a dis­closed, con­trac­ted, long-dated price for green am­mo­nia in either re­gion. Mode 2A Tranche I awar­ded 724,000 tpa across 13 fer­til­iser plants on ten-year fixed-price agree­ments, with SECI act­ing as in­ter­me­di­ary pro­curer so that in­di­vidual fer­til­iser plants did not have to carry coun­ter­party risk on a first-of-its-kind sup­plier. The band was Rs 49.75 to 64.74 per kg de­livered, with a weighted av­er­age of Rs 53.27 per kg, or about USD 604 per t. The low­est lot was ACME sup­ply­ing IFFCO Paradeep at 100,000 tpa and Rs 49.75 per kg; the highest was ACME sup­ply­ing In­dorama Hal­dia at 20,000 tpa and Rs 64.74 per kg (SECI; PIB re­lease 2153006, 6 Au­gust 2025).

No Gulf contract price has ever been published, and that absence is a finding rather than a gap in the record.

Round two of the same scheme is the single most con­sequen­tial price dis­clos­ure still pending for either re­gion. AM Green's phase 2 won the Asian lot as sole win­ner on 30 Septem­ber 2026, with Hintco com­mit­ting to buy a min­imum of EUR 585m of am­mo­nia over ten years from 2029. The per-tonne price has been with­held until Hintco pub­lishes all lots, which it has said it will do be­fore the end of 2026. Until then it ex­ists as a con­tract value without a unit price, and no in­fer­ence about the per-tonne fig­ure should be drawn from the ag­greg­ate.

Refinery hydrogen, and the silence from the Gulf

The third series is In­dian re­finery hy­dro­gen, and it is the least clean of the three. In­dian Oil's re­finery hy­dro­gen auc­tion cleared at Rs 397 per kg, about USD 4.67 per kg, on a 25-year off­take (re­por­ted via IEEFA, June 2025). A low­est re­finery print of Rs 279 per kg is also re­por­ted (Busi­ness Stand­ard, 3 Novem­ber 2026), and the IEA tab­u­lates the In­dian re­finery awards near Rs 328 per kg, about USD 3.8 per kg, in its Global Hy­dro­gen Re­view 2025. Three fig­ures, three sources, no re­con­cili­ation. What can safely be said is that In­dian re­finery hy­dro­gen has cleared between Rs 279 and Rs 397 per kg on very long ten­ors.

The si­lence from the Gulf is there­fore total, and it is worth stat­ing pre­cisely what is si­lent. No price is pub­lic

for the Air Products and NEOM agree­ment, al­though SEC fil­ings con­firm the ar­range­ment is fixed-price. No price is pub­lic for ACME Duqm's sup­ply to Yara. No price is pub­lic for the ADNOC and Fer­ti­globe cargo to Mit­sui, nor for any TA'ZIZ volume, nor for any awar­ded Omani block. Ara­mco has no term agree­ment to price. Gas trans­fer prices to Gulf pro­du­cers, which de­cide blue and grey cost en­tirely, are not pub­lic either, so even a re­con­struc­ted cost bench­mark is un­avail­able.

A fourth num­ber is often quoted along­side these and is not a price at all. Re­li­ance bid Rs 24.99 per kg for 49,000 tpa in SIGHT Mode 1 Tranche II (JMK Re­search, 21 March 2025). That is a bid for a pro­duc­tion in­cent­ive, ex­pressed as the sub­sidy per kilo­gram the bid­der is will­ing to ac­cept, and it is not com­par­able with a de­livered con­tract price. Mix­ing the two pro­duces a false im­pres­sion of In­dian cost levels.

No Argus or Platts as­sessed green or blue am­mo­nia level, and no at­trib­ut­able cur­rent Middle East free-on-board am­mo­nia print, could be ob­tained: both sit be­hind sub­scrip­tion. The Korean CHPS round one clear­ing price is un­dis­closed.

The takeaway is un­com­fort­able but ac­tion­able. A buyer ne­go­ti­at­ing Gulf-ori­gin am­mo­nia today has no re­gional com­par­ator and must price against In­dian and European dis­cov­ery: a ten-year In­dian fixed price av­er­aging about USD 604 per t, a European pilot clear­ing at EUR 1,000 per t de­livered, and an In­dian re­finery band of Rs 279 to 397 per kg. Each of those ref­er­ences car­ries a dif­fer­ent tenor, a dif­fer­ent de­liv­ery point and a dif­fer­ent sub­sidy struc­ture, so none is a clean sub­sti­tute. The prac­tical con­sequence is that the first party to pub­lish a Gulf con­tract price will reset the ne­go­ti­at­ing po­s­i­tion for every sub­sequent cargo, and that until one does, every Gulf quo­ta­tion is being tested against for­eign evid­ence.

What the premium actually is, and why the number moves

India's discovered green ammonia price sits between about 10 and 31 per cent above grey, depending entirely on which grey reference is chosen. For part of 2026 it sat below spot grey altogether.

The hon­est state­ment of the green premium is that it is as much a choice of ref­er­ence as a meas­ure­ment. India's dis­covered green am­mo­nia av­er­age of about USD 601 to 604 per t sits against grey am­mo­nia at USD 515 per t as at March 2025, a pub­lished gap of about USD 86 to 126 per t, or between roughly 10 and 31 per cent de­pend­ing on which green print and which grey ref­er­ence is used (IEEFA, Novem­ber 2025; JMK Re­search via pv magazine India, 28 Au­gust 2025). IEEFA states about 31 per cent against a grey range of USD 400 to 515 per t. Tampa cost-and-freight

GCC & India HydrogenVolge Quarterly15 •

set­tle­ments dur­ing 2026 ran USD 555 to 825 per t (Fer­til­izer Daily and QCIntel, Janu­ary to Novem­ber 2026), so for part of 2026 the In­dian green print was below spot grey and the premium, meas­ured that way, was neg­at­ive.

Reference usedFigureDate and sourcePremium that results
Indian discovered green ammonia, weighted averageAbout USD 601 to 604 per tSECI Mode 2A award, 2025The green side of every comparison below
Grey ammonia, single published printUSD 515 per tAs at March 2025About USD 86 to 126 per t, or roughly 10 to 31 per cent
Grey ammonia, rangeUSD 400 to 515 per tIEEFA, November 2025About 31 per cent, on IEEFA's own statement
Tampa cost-and-freight settlementsUSD 555 to 825 per tFertilizer Daily and QCIntel, January to November 2026Negative for part of 2026
Pre-auction expectationUSD 707 to 715 per tIEEFANearly twice grey; not realised
Green steel, modelledRs 55,000 to 65,000 per tIEEFA, source of the estimate unnamedAbout 20 to 30 per cent above conventional

The green steel fig­ure is a mod­elled es­tim­ate and IEEFA does not name the source of the es­tim­ate. It is re­por­ted here on that basis and should not be treated as a trans­acted price.

Why does the num­ber move so vi­ol­ently? Be­cause the green side is a fixed ten-year con­tract price and the grey side is a volat­ile spot as­sess­ment driven by gas. The In­dian green print is a single num­ber, set once, for a dec­ade, under a pro­cure­ment in which the state in­ter­me­di­ated coun­ter­party risk. Grey am­mo­nia at Tampa moved across a range of USD 270 per t within a single year. Com­par­ing a fixed dec­ade-long price with a spot series will pro­duce a dif­fer­ent premium every month, and in a soft gas year no premium at all. This is not a present­a­tional trick: it is the arith­metic con­sequence of com­par­ing two in­stru­ments of en­tirely dif­fer­ent char­ac­ter.

The second reason the num­ber moves is that the ex­pec­ted premium was wrong, and by a wide mar­gin. Pre-auc­tion ex­pect­a­tion had been USD 707 to 715 per t, de­scribed as nearly twice grey (IEEFA). The auc­tion cleared at about USD 604 per t on a weighted av­er­age basis. The dis­covered price came in roughly 15 per cent below the ex­pect­a­tion built into most pub­lished ana­lysis of In­dian green am­mo­nia, so a buyer mod­el­ling the premium on pre-auc­tion con­sensus would have over­stated it sub­stan­tially.

The premium is as much a choice of reference as a measurement, and in a soft gas year it can disappear entirely.

The cost stack beneath the price, and what cannot be seen

Be­neath the con­trac­ted prices sits a cost stack that is pub­lished only as ranges. IEEFA, in Novem­ber 2025, gives grey hy­dro­gen at USD 1.5 to 3 per kg against green at USD 3 to 6 per kg, with In­dian solar tar­iffs at Rs 2.5 to 3 per kWh and elec­tro­lyser cap­ital cost at Rs 26,500 to 106,000 per kW. That elec­tro­lyser range is a factor of four, which is to say that the pub­lished cost of green hy­dro­gen in India is dom­in­ated by an input nobody can price within a factor of four. GPCA, in March 2025, gives Gulf blue hy­dro­gen at USD 2.8 to 3.5 per kg de­pend­ing on gas prices, with the gas as­sump­tion un­stated.

That un­stated gas as­sump­tion is the single largest hole in the Gulf cost case. Gas trans­fer prices to Gulf pro­du­cers de­cide blue and grey cost en­tirely, and they are not pub­lic. No Gulf grey hy­dro­gen cost is pub­lic. No blue am­mo­nia lev­el­ised cost is pub­lic for either re­gion. A Gulf blue am­mo­nia pro­ject there­fore presents a cost range whose dom­in­ant vari­able is un­dis­closed, so the range can­not be in­de­pend­ently tested and its lower bound can­not be re­lied upon.

The IEA's for­ward pro­jec­tions should be read with the same care. The Global Hy­dro­gen Re­view 2026 states that by 2030 the Middle East, India and Chile could reach just above USD 3 per kg, and that gas-rich re­gions could reach po­ten­tially just above USD 1 per kg for blue hy­dro­gen, a fig­ure the IEA it­self qual­i­fies as largely the­or­et­ical, with no live pro­ject meet­ing it at 95 per cent cap­ture. These are mod­elled pro­jec­tions, not quo­ta­tions. The as­sump­tion annex car­ry­ing weighted av­er­age cost of cap­ital, ca­pa­city factor, elec­tro­lyser cap­ital cost and gas price could not be re­trieved, so the fig­ures are quoted here as ranges without their as­sump­tions, which is how they should be used.

The fre­quently quoted fram­ing of USD 4 to 5 per kg fall­ing to USD 2 per kg for India could not be traced to any MNRE or NITI Aayog doc­u­ment. Its only ob­serv­able an­chors are the Rs 397 per kg award and gov­ern­ment pro­jec­tions of Rs 260 to 310 per kg re­por­ted second­hand. It should not be cited as of­fi­cial.

The IEA's 2025 edi­tion adds a point that cuts dir­ectly against the Gulf green case. It tab­u­lates the In­dian re­finery awards near Rs 328 per kg, about USD 3.8 per kg, and notes that in cheap-gas re­gions in­clud­ing the Middle East the green-to-grey gap will re­main lar­ger, and that car­bon cap­ture is like­lier to be com­pet­it­ive in the near term. The im­plic­a­tion is un­com­fort­able for green Gulf ex­port­ers and com­fort­able for blue ones: the cheaper the do­mestic gas, the wider the premium a green mo­lecule must bridge.

The de­mand-side arith­metic is harsher still. The IEA's 2026 edi­tion states that ab­sent policy sup­port the

GCC & India HydrogenVolge Quarterly16 •

max­imum ac­cept­able hy­dro­gen cost is below USD 2 per kg for most sec­tor and re­gion com­bin­a­tions, and that for steel the hy­dro­gen cost must be neg­at­ive to reach par­ity. Set that against a pub­lished green range of USD 3 to 6 per kg and the gap is not a premium to be ab­sorbed in a pro­cure­ment de­cision: it is a gap that only a sub­sidy, a man­date or a car­bon price can close.

The takeaway for a buyer is to fix the ref­er­ence be­fore ne­go­ti­at­ing the premium. A ten-year fixed price should be com­pared with a ten-year grey for­ward view, not with last week's Tampa set­tle­ment, and the com­par­ison should be stated with its ref­er­ence at­tached every time. Where a coun­ter­party quotes a premium without nam­ing its grey ref­er­ence and its date, the quo­ta­tion is not a meas­ure­ment. On the re­cord for 2025 and 2026, the same In­dian green price sup­ports a premium of about 31 per cent, one of about 10 per cent, or none at all.

Who is actually obliged to buy

Across India, the European Union, Japan, Korea and the IMO, binding purchase obligation is far scarcer than the headline targets suggest. India has notified none at all.

The ques­tion that de­cides whether this sec­tor has a mar­ket is who is leg­ally ob­liged to buy, and the an­swer is that very few parties are. India has no­ti­fied no green hy­dro­gen or green am­mo­nia con­sump­tion ob­lig­a­tion for re­fin­ing, fer­til­iser or steel. Japan's scheme binds the gov­ern­ment to pay rather than any party to buy. Korea's second clean hy­dro­gen auc­tion was can­celled on its bid dead­line day. The IMO's Net-Zero Frame­work is not ad­op­ted. The European Union is the ex­cep­tion that proves the point: RED III and FuelEU Mari­time are bind­ing, and they are the only in­stru­ments in this sur­vey that com­pel a pur­chase. Tar­get, ob­lig­a­tion and gov­ern­ment pay­ment are three dif­fer­ent things and are sep­ar­ated below.

JurisdictionInstrumentLegal characterWhat it actually bindsStatus as at November 2026
IndiaGreen hydrogen or ammonia consumption obligationNone notifiedNothingDiscussed for years and yet to be notified, per counsel quoted in Business Standard, 3 November 2026
IndiaSECI SIGHT Mode 2A procurementContractThe 13 fertiliser plants that signed670,000 tpa of the 724,000 tpa awarded signed March 2026
JurisdictionInstrumentLegal characterWhat it actually bindsStatus as at November 2026
IndiaCarbon Credit Trading SchemeBinding intensity targets208 units notified in tranche 2; about 490 entities in totalNotified 8 October 2025 and mid-January 2026; iron and steel still draft at a revised notification of 26 June 2026
IndiaGreen Steel Taxonomy, S.O. 763(E)LabellingNobody to buy anythingNotified December 2024
IndiaGreen Hydrogen Certification SchemeVoluntary labelling at 2 kg CO2e per kgNothingMNRE, April 2025; portal live 17 June 2026
European UnionRED III Article 22aBinding on member states42 per cent of industrial hydrogen to be RFNBO by 2030, 60 per cent by 2035, 1 per cent in transportTransposition due 21 May 2025; only eight of 27 member states had both industry and transport mandates in national law as at mid-2026
European UnionFuelEU MaritimeBinding on ship operatorsMinus 2 per cent well-to-wake intensity from 2025, minus 6 per cent from 2030, minus 14.5 per cent from 2035In application since 1 January 2025
JapanHydrogen Society Promotion Act 2024Binds the government to pay15 years of contract-for-difference price-gap support against the incumbent fuelCertifications announced 30 September 2025, 19 December 2025 and 27 March 2026
Japan20 per cent ammonia co-firingPolicy target from the 2021 Strategic Energy PlanNothingFour coal units plan commercial 20 per cent operation between FY2027 and FY2030; Hekinan Unit 4 is the only unit to have demonstrated it at scale
KoreaCHPS clean hydrogen auctionContract where awarded750 GWh of the 6,500 GWh per year offered in round oneRound two, 3,000 GWh per year, cancelled 17 October 2025; 2026 volume cut to 500 GWh per year
IMONet-Zero FrameworkNot adoptedNothing yetAdoption sits at the resumed extraordinary session of 4 December 2026
GCC & India HydrogenVolge Quarterly17 •

India first, be­cause the gap between per­cep­tion and po­s­i­tion is widest there. There is no no­ti­fied green hy­dro­gen or green am­mo­nia con­sump­tion ob­lig­a­tion for re­fin­ing, fer­til­iser or steel. Busi­ness Stand­ard, on 3 Novem­ber 2026, quotes coun­sel dir­ectly to the ef­fect that the ob­lig­a­tion has been dis­cussed for years but is yet to be no­ti­fied. The 5 per cent by 2029-30 and 10 per cent by 2035-36 re­finery fig­ures that cir­cu­late widely could not be traced to any no­ti­fic­a­tion or of­fi­cial pro­posal: all cir­cu­lat­ing num­bers are drafts. One blog claim of a no­ti­fied pur­chase ob­lig­a­tion is con­tra­dicted by the primary re­cord and should be treated as wrong.

What India has in­stead is pro­cure­ment, which is stronger for the sup­pli­ers who win it and weaker for the mar­ket as a whole. The 724,000 tpa SECI am­mo­nia award is a con­tract, bind­ing on the 11 plants that signed in March 2026. A fur­ther 30,000 tpa of re­finery hy­dro­gen has been pro­cured for IOCL, BPCL, HPCL and Nu­m­a­l­igarh, and SECI has stated an in­tent to pro­cure 1 Mtpa more for fer­til­iser (IGHA, Au­gust 2026). An in­tent to pro­cure is not an ob­lig­a­tion to con­sume, and pro­cure­ment can be paused, re­tend­ered or scrapped, as SECI's own can­cel­la­tion of its two hub pro­pos­als in July 2025 demon­strates.

India's demand is a procurement programme, not a purchase obligation, and a procurement programme can be paused.

India does, how­ever, have bind­ing ad­ja­cent in­stru­ments, and these are where pres­sure will first be felt. The Car­bon Credit Trad­ing Scheme no­ti­fied in­tens­ity tar­gets on 8 Oc­to­ber 2025 for alu­minium, ce­ment, chlor-al­kali and pulp and paper, and in mid-Janu­ary 2026 for re­fin­ing, pet­ro­chem­ic­als and tex­tiles, cov­er­ing 208 units, with com­pli­ance years 2025-26 and 2026-27 meas­ured against an FY2023-24 baseline and about 490 en­tit­ies in total; iron and steel re­mained draft at a re­vised no­ti­fic­a­tion of 26 June 2026 (ICAP). The scheme pub­lishes no hy­dro­gen volume, so it cre­ates a price on in­tens­ity without spe­cify­ing the abate­ment route. The Green Steel Tax­onomy is no­ti­fied but binds nobody to buy, and the Green Hy­dro­gen Cer­ti­fic­a­tion Scheme is vol­un­tary la­belling at a 2 kg CO2e per kg threshold.

Japan pays, Korea retreated, and the IMO has not voted

Japan's Hy­dro­gen So­ci­ety Pro­mo­tion Act of 2024 is the most gen­er­ous in­stru­ment in this sur­vey and the most

fre­quently mis­described. It provides fif­teen years of con­tract-for-dif­fer­ence sup­port cov­er­ing the price gap against the in­cum­bent fuel, with cer­ti­fic­a­tions an­nounced on 30 Septem­ber 2025, 19 Decem­ber 2025 and 27 March 2026. It binds the gov­ern­ment to pay. It does not bind any party to buy. The much-quoted 20 per cent am­mo­nia co-fir­ing fig­ure is a policy tar­get from the 2021 Stra­tegic En­ergy Plan and not a bind­ing ob­lig­a­tion: only four coal units plan com­mer­cial 20 per cent op­er­a­tion between FY2027 and FY2030, and Hek­inan Unit 4 is the only unit to have demon­strated 20 per cent co-fir­ing at scale (IEEFA).

Korea has moved in the op­pos­ite dir­ec­tion. The CHPS mech­an­ism is a con­tract­ing scheme, and its first round offered 6,500 GWh per year and awar­ded 750 GWh, about 11 per cent, to KOSPO Samcheok on im­por­ted blue am­mo­nia sup­plied by Sam­sung C and T, at an un­dis­closed clear­ing price. Round two, at 3,000 GWh per year, was can­celled by KPX on 17 Oc­to­ber 2025, on the bid dead­line day. The volume was then cut to 500 GWh per year of clean hy­dro­gen for 2026, and coal-am­mo­nia co-fir­ing will be ex­cluded from CHPS al­to­gether (Seoul Eco­nomic Daily, 9 June 2026). A buyer count­ing on Korean am­mo­nia co-fir­ing de­mand is count­ing on a scheme that has shrunk by an order of mag­nitude and has re­moved the use case.

The IMO is the largest single po­ten­tial de­mand cre­ator in this sur­vey and it has not voted. The Net-Zero Frame­work was ap­proved in prin­ciple at MEPC 83 in April 2025, with 63 in fa­vour. Ad­op­tion failed at the Oc­to­ber 2025 ex­traordin­ary ses­sion when a Saudi mo­tion to ad­journ for twelve months passed 57 to 49. MEPC 84, held from 27 April to 1 May 2026, did not adopt the frame­work but car­ried it for­ward as the sole basis for work. Ad­op­tion now sits at the re­sumed ex­traordin­ary ses­sion of 4 Decem­ber 2026 (Car­bon Brief Q and A, 5 May 2026, up­dated 15 July 2026; Seat­rade and Lloyd's Re­gister). If ad­op­ted in Decem­ber 2026, the earli­est entry into force is 1 March 2028 under MARPOL tacit ac­cept­ance.

IMO primary doc­u­ments could not be con­sul­ted: imo.org served empty re­sponses. The IMO po­s­i­tions above rest on Car­bon Brief, Seat­rade and Lloyd's Re­gister re­port­ing.

The ap­proved tra­ject­ory, should it be ad­op­ted, would re­quire a base in­tens­ity re­duc­tion of 4 per cent in 2028 rising to 30 per cent in 2035, with a dir­ect tar­get of 17 to 43 per cent against 2008, and re­medial units priced at USD 100 and USD 380. That would be a mean­ing­ful car­bon price on mar­ine fuel. It is also con­di­tional on a vote that has already been ad­journed once at the in­stance of a Gulf state. FuelEU Mari­time, by con­trast, is bind­ing and has been in ap­plic­a­tion since 1 Janu­ary 2025.

GCC & India HydrogenVolge Quarterly18 •

The takeaway is that one jur­is­dic­tion com­pels pur­chase and the rest either pay, as­pire or have not de­cided. For an ex­porter from the Gulf or India, that con­cen­trates com­mer­cial risk severely: the only re­li­able ob­lig­ated de­mand is European, and it is being trans­posed into na­tional law slowly. A pro­ject whose busi­ness case as­sumes Ja­pan­ese, Korean or In­dian ob­lig­a­tion is as­sum­ing some­thing that does not cur­rently exist in law.

Europe's rulebook as the real gate

The only binding demand in this survey is European, which makes European rules the gate every Gulf and Indian exporter must pass. RED III, the RFNBO delegated act and CBAM decide what a molecule is worth.

Be­cause Europe is the only jur­is­dic­tion in this sur­vey that com­pels a pur­chase, European rules, and not Gulf or In­dian am­bi­tion, de­term­ine what an ex­por­ted mo­lecule is worth. Three in­stru­ments do the work: RED III Art­icle 22a, which ob­liges mem­ber states to reach 42 per cent RFNBO in in­dus­trial hy­dro­gen by 2030; the RFNBO del­eg­ated act, which de­cides whether a mo­lecule qual­i­fies at all, with hard dates in 2028 and 2030; and CBAM, whose defin­it­ive re­gime began on 1 Janu­ary 2026 with hy­dro­gen in scope and whose free al­loc­a­tion lad­der des­cends to zero by 2034. A Gulf ex­porter is selling into that, and com­pli­ance with it is the product.

YearCBAM free allocation retainedOther binding change in the same year
202697.5 per centDefinitive regime begins 1 January, hydrogen in scope; the 50 t de minimis does not apply to hydrogen or electricity
2027Not stated in the sources used hereCBAM certificate pricing moves to the weekly average ETS price from 1 January
2028Not stated in the sources used hereRFNBO additionality grandfathering ends 1 January; scheduled review of the RFNBO methodology in July
2030About 51.5 per centHourly temporal correlation applies from 1 January; RED III 42 per cent industrial and 1 per cent transport targets bite; FuelEU zero-emission at berth in AFIR-covered ports from 1 January
2034ZeroFuelEU Article 5(3) 2 per cent RFNBO sub-quota applies from 1 January if the 2031 RFNBO share is below 1 per cent

CBAM factors for 2027, 2028 and in­ter­ven­ing years were not re­trieved and are not in­ter­pol­ated here. A re­por­ted Com­mis­sion pro­posal to re­in­state 15 per cent free al­loc­a­tion from 2028 and ex­tend the phase-out to 2038 is un­cor­rob­or­ated and should not be planned around.

RED III Art­icle 22a is bind­ing on mem­ber states and sets the de­mand that a Gulf or In­dian ex­porter is ul­ti­mately selling into: re­new­able fuels of non-bio­lo­gical ori­gin to be at least 42 per cent of in­dus­trial hy­dro­gen

by 2030 and 60 per cent by 2035, with a sep­ar­ate 1 per cent trans­port tar­get (Dir­ect­ive (EU) 2023/2413). Two qual­i­fic­a­tions are com­mer­cially sig­ni­fic­ant. Trans­pos­i­tion was due on 21 May 2025 and only eight of 27 mem­ber states had both in­dustry and trans­port man­dates in na­tional law as at mid-2026 (European Hy­dro­gen Ob­ser­vat­ory, 2026). And re­finery hy­dro­gen falls to the 1 per cent trans­port ob­lig­a­tion rather than the 42 per cent, which re­moves Europe's largest ex­ist­ing hy­dro­gen con­sumer from the stronger man­date.

The del­eg­ated act, 2023/1184, is the gate it­self, and it is already bind­ing. Ad­di­tion­al­ity does not apply to elec­tro­lys­ers com­mis­sioned be­fore 1 Janu­ary 2028, which cre­ates a hard com­mis­sion­ing dead­line with real eco­nomic value at­tached: an elec­tro­lyser en­er­gised on 31 Decem­ber 2027 is grand­fathered and one en­er­gised a day later is not. Tem­poral cor­rel­a­tion is monthly to the end of 2029 and hourly from 1 Janu­ary 2030, which is a sig­ni­fic­ant change in how a plant must be dis­patched and con­trac­ted against re­new­able gen­er­a­tion. A Com­mis­sion re­vi­sion ex­tend­ing the trans­ition to 2035 is a pro­posal only and car­ries no legal ef­fect at present.

An electrolyser energised on 31 December 2027 is grandfathered against additionality and one energised a day later is not.

For an ex­porter, the prac­tical ef­fect of those two dates is that the del­eg­ated act, rather than any Gulf or In­dian scheme, sets the con­struc­tion sched­ule. A pro­ject aim­ing to sell RFNBO-com­pli­ant am­mo­nia into the European com­pli­ance mar­ket has a com­mis­sion­ing tar­get of 1 Janu­ary 2028 for the grand­fath­er­ing be­ne­fit and a dis­patch re­design due by 1 Janu­ary 2030 for hourly match­ing. It is to be noted that ACME Duqm is pre-cer­ti­fied as RFNBO-com­pli­ant and AM Green Kak­in­ada holds CertifHy RFNBO pre-cer­ti­fic­a­tion: com­pet­it­ive ad­vant­age cur­rently lies in cer­ti­fic­a­tion rather than ca­pa­city. A sched­uled re­view of the RFNBO meth­od­o­logy falls in July 2028, which in­tro­duces a known reg­u­lat­ory event in­side the life of every con­tract now being signed.

CBAM, and the rulebook already deciding projects

CBAM's defin­it­ive re­gime began on 1 Janu­ary 2026 with hy­dro­gen in scope, and its design reaches fur­ther into Gulf and In­dian in­dustry than hy­dro­gen alone. The 50 t de min­imis threshold does not apply to hy­dro­gen or elec­tri­city, so there is no small-con­sign­ment

GCC & India HydrogenVolge Quarterly19 •

es­cape. The CBAM factor, which is the pro­por­tion of free al­loc­a­tion re­tained by European pro­du­cers and there­fore the pro­por­tion of the car­bon cost not yet charged at the bor­der, starts at 97.5 per cent in 2026, falls to about 51.5 per cent in 2030 and reaches zero from 2034. From 1 Janu­ary 2027, cer­ti­fic­ate pri­cing moves to the weekly av­er­age ETS price, which re­moves a smooth­ing mech­an­ism and trans­mits European car­bon price volat­il­ity dir­ectly into an ex­porter's landed cost.

The con­sequence for the Gulf and India is that CBAM binds European im­port­ers and there­fore binds ex­port­ers of am­mo­nia, fer­til­iser and steel com­mer­cially, even though it im­poses no ob­lig­a­tion on them in their own law. It works by chan­ging what a European buyer can af­ford to pay for a high-car­bon tonne rather than by pro­hib­it­ing its pro­duc­tion. As the factor des­cends, the ad­vant­age of a cer­ti­fied low-car­bon tonne rises mech­an­ic­ally, without any new policy being made. That is the most pre­dict­able source of de­mand growth avail­able to either re­gion.

It should be re­cor­ded that the rule­book is already de­cid­ing pro­jects, and not only at the mar­gin. Equi­nor and Linde can­celled H2M Eem­shaven, a 1 GW pro­ject at about 210,000 tpa, as re­por­ted on 20 Feb­ru­ary 2026, cit­ing among other things RED III's treat­ment of blue hy­dro­gen (Hy­dro­gen In­sight). That is a European pro­ject can­celled by European rules, which is the clearest avail­able evid­ence that the del­eg­ated act and the dir­ect­ive are op­er­at­ive con­straints rather than as­pir­a­tions. An ex­porter choos­ing between blue and green for a European-fa­cing pro­ject should treat that can­cel­la­tion as the gov­ern­ing pre­ced­ent.

Ship­ping adds a second European layer. FuelEU Mari­time binds op­er­at­ors of ships above 5,000 gross tonnes call­ing at European ports under any flag, with its first an­nual re­port, cov­er­ing 2025, due on 31 Janu­ary 2026 and re­cur­ring there­after. The in­tens­ity tra­ject­ory runs minus 2 per cent from 2025, minus 6 per cent from 2030 and minus 14.5 per cent from 2035. RFNBO en­ergy counts double to 31 Decem­ber 2033, which front-loads the value of early RFNBO bunk­er­ing, and from 1 Janu­ary 2030 zero-emis­sion at berth ap­plies in AFIR-covered ports. Under Art­icle 5(3), a 2 per cent RFNBO sub-quota ap­plies from 1 Janu­ary 2034 if the RFNBO share in 2031 is below 1 per cent, which con­verts a short­fall into a man­date auto­mat­ic­ally.

The takeaway is that the European rule­book, not the Gulf's re­source en­dow­ment, is the asset that a Gulf or In­dian pro­ject most needs to se­cure. Cer­ti­fic­a­tion status, com­mis­sion­ing date re­l­at­ive to 1 Janu­ary 2028, dis­patch design re­l­at­ive to 1 Janu­ary 2030, and the CBAM ex­pos­ure of the buyer's own product de­cide whether a tonne sells into ob­lig­ated de­mand at a premium or into un­oblig­ated de­mand at the grey price. Very few an­nounced pro­jects in either re­gion have ad­dressed all four, and the two fur­thest ad­vanced on cer­ti­fic­a­tion are both In­dian-owned.

The reality check: a sector revising itself downward

The IEA's own 2030 projection has fallen 45 per cent in two editions. Every major forecaster has cut, and the write-offs carry figures filed with regulators.

The most use­ful single piece of evid­ence avail­able to a buyer is not any fore­cast but the dir­ec­tion in which the fore­casts have moved. The IEA's es­tim­ate of po­ten­tial 2030 low-emis­sions hy­dro­gen pro­duc­tion from an­nounced pro­jects rose from over 17 Mt in 2021 to 49 Mt in 2024, then fell to 37 Mt in 2025, the first ever de­cline, and to 27 Mt in 2026: a cut of 45 per cent in two edi­tions. BloombergNEF cut its 2030 global clean hy­dro­gen sup­ply es­tim­ate from 16.4 Mt per year to about 5.5 Mt per year. DNV cut its mid-cen­tury clean hy­dro­gen fore­cast by 45 per cent against its 2022 fore­cast. The sec­tor is not being re­vised down­ward by its crit­ics. It is being re­vised down­ward by its own in­sti­tu­tions.

IEA editionPotential 2030 low-emissions production from announced projectsShare or volume at final investment decision
2021Over 17 MtNot stated
202216 to 24 Mt4 per cent
202338 Mt4 per cent
202449 Mt3.4 Mtpa
202537 Mt, the first ever decline9 per cent
202627 MtOnly about 300 ktpa of new FID taken in the year

Read as a series rather than as a set of an­nual head­lines, the IEA num­bers de­scribe a pipeline that in­flated and then de­flated while the com­mit­ted por­tion of it barely moved. The share at FID was 4 per cent in 2022 and 4 per cent in 2023; the 2024 edi­tion gives 3.4 Mtpa at FID; the 2025 edi­tion gives 9 per cent. The 2026 edi­tion is the sharpest line avail­able to a buyer any­where in the pub­lic re­cord: com­mit­ted plus strong-po­ten­tial 2030 volume fell from 10 Mt to just above 6 Mt, only about 300 ktpa of new FID was taken, and 22 Mt of an­nounced pro­duc­tion may lose any chance to

GCC & India HydrogenVolge Quarterly20 •

begin op­er­a­tion by 2030 if in­vest­ment de­cisions are not taken by early 2027.

Two fur­ther fig­ures from the same edi­tion de­serve to be set be­side one an­other. Signed agree­ments in 2025 totalled about 1.7 Mt, of which only about 20 per cent is firm. In­stalled elec­tro­lysis doubled in 2025 to over 4 GW, with China ac­count­ing for about 75 per cent of ad­di­tions. The first says that the paper flow has con­tin­ued while its bind­ing con­tent has not. The second says that the elec­tro­lysis ac­tu­ally being in­stalled is being in­stalled some­where other than the Gulf or India.

The pipeline inflated and deflated while the committed portion of it barely moved.

The private fore­casters tell the same story in their own terms. BloombergNEF cut global clean hy­dro­gen sup­ply in 2030 from 16.4 Mt per year, as at 14 May 2024, to about 5.5 Mt per year, as at 5 Novem­ber 2025, which in BNEF's own words is half of what was ex­pec­ted just a few years ago. The Hy­dro­gen Coun­cil and McKinsey, in the Global Hy­dro­gen Com­pass of Septem­ber 2025, re­cord the most in­struct­ive pair­ing in the lit­er­at­ure: com­mit­ted post-FID in­vest­ment to 2030 rose from USD 10bn in Decem­ber 2020 to USD 110bn in July 2025, while feas­ible 2030 sup­ply fell to 9 to 14 Mtpa, or 20 to 30 per cent of an­nounced. Bind­ing off­take stood at 3.6 Mtpa, and over 50 pro­jects had been pub­licly can­celled in the eight­een months to July 2025.

That pair­ing is the cent­ral fact of the sec­tor: com­mit­ted cap­ital rose el­ev­en­fold while the volume it is ex­pec­ted to pro­duce fell. The com­mit­ted money has gone into fewer, lar­ger, bet­ter-con­trac­ted pro­jects, and the long tail has been writ­ten down. West­wood quan­ti­fies the tail in Europe: 23 pro­jects and 29.2 GW can­celled or stalled by the end of 2024, 20.3 per cent of a 111.5 GW pipeline (17 Decem­ber 2024), and then an ex­pect­a­tion that only 17 per cent of the EU pipeline, about 12 GW, would ma­ter­i­al­ise by 2030 (1 April 2025).

The write-offs, with the figures as filed

The write-offs can­not be presen­ted as sen­ti­ment, be­cause they are filed with reg­u­lat­ors and carry num­bers. Air Products can­celled Massena, World En­ergy Para­mount and a Texas car­bon monox­ide pro­ject on 24 Feb­ru­ary 2025 at a pre-tax charge not ex­ceed­ing USD 3.1bn (8-K). It then ex­ited the Louisi­ana Clean En­ergy Com­plex and Casa Grande, de­cided on 26 June 2026, at a pre-tax charge of up to USD 2.9bn and a cash cost not ex­ceed­ing USD 925m, and the stated reason is the single most im­port­ant sen­tence in this

sur­vey: it could not se­cure firm hy­dro­gen and ni­tro­gen off­take and could not di­vest the am­mo­nia loop (8-K Item 2.06, 30 June 2026).

A cir­cu­lat­ing fig­ure of USD 3.2bn for the Air Products charge ex­ceeds the com­pany's own stated ceil­ing and is un­veri­fied. NEOM was ex­pli­citly re­tained in both fil­ings and is not part of either write-off.

BP can­celled HyGreen Teesside, 500 MW, in March 2025 and scrapped H2Teesside, up to 1.2 GW, in 2026, cit­ing a com­pet­ing data centre con­sent and de­teri­or­at­ing de­mand across the hy­dro­gen sec­tor. The data centre point re­curs: Mas­dar re­dir­ec­ted 6 GW of solar ear­marked for am­mo­nia to ar­ti­fi­cial in­tel­li­gence data centres in Au­gust 2026. Equi­nor and Linde can­celled H2M Eem­shaven, 1 GW and about 210,000 tpa, as re­por­ted on 20 Feb­ru­ary 2026. Shell scrapped its Rot­ter­dam bio­fuels and blue hy­dro­gen com­plex in 2025 after USD 1.4bn had been spent. It should be re­cor­ded that Hol­land Hy­dro­gen II is not con­firmed can­celled and that Hol­land Hy­dro­gen I, 200 MW, con­nec­ted to the Dutch net­work in March 2026, so the European re­cord is not uni­formly neg­at­ive.

What should a buyer take from a sec­tor that has re­vised it­self down by this much? Not that it will fail, but that the base rate of de­liv­ery against an­nounce­ment is now meas­ur­able and low. On the Hy­dro­gen Coun­cil's own arith­metic, feas­ible 2030 sup­ply is 20 to 30 per cent of an­nounced. On West­wood's, 17 per cent of the European pipeline will ma­ter­i­al­ise. On the IEA's, 9 per cent of the 2025 pipeline had reached FID. Three in­de­pend­ent es­tim­ates con­verge on between one fifth and one tenth of an­nounced ca­pa­city.

The takeaway is a dis­count rate ap­plied to an­nounce­ments rather than a ver­dict on the tech­no­logy. A pro­ject list should be read with the de­liv­ery base rate at­tached, and the base rate should be ap­plied to the an­nounced tier spe­cific­ally, be­cause the pro­du­cing, com­mis­sion­ing and under-con­struc­tion tiers have already passed the test the base rate meas­ures. Ap­plied that way, the Gulf and In­dian pipelines look smal­ler but firmer than the head­line ca­pa­city sug­gests: a hand­ful of as­sets that will exist, and a long list that mostly will not.

Subsidy, and what it is worth to a buyer

Three jurisdictions have published quantified support and two of the most-discussed have published none. What matters is not the headline envelope but the fraction actually disbursed, which in India is under 1.5 per cent.

Sub­sidy de­cides whether these mo­lecules clear, and the po­s­i­tion is that the pub­lished en­vel­opes are large while the dis­burse­ments are small or ab­sent. India has com­mit­ted Rs 19,744 crore and had spent Rs

GCC & India HydrogenVolge Quarterly21 •

292 crore by Au­gust 2026, under 1.5 per cent, with no SIGHT in­cent­ive claimed or paid as at July 2026 be­cause noth­ing sup­por­ted under the scheme had been fully com­mis­sioned. The EU Hy­dro­gen Bank has cleared three auc­tions and is pub­lish­ing its own at­tri­tion. Japan has an en­vel­ope of about JPY 3 tril­lion over fif­teen years. Saudi Ar­a­bia and the United Arab Emir­ates have no pub­licly quan­ti­fied pro­duc­tion sup­port of any kind, and that ab­sence is it­self a find­ing a buyer should price.

JurisdictionInstrumentEnvelope as publishedPer-unit supportWhat has actually been paid or signed
IndiaNational Green Hydrogen Mission and SIGHTRs 19,744 crore total; SIGHT Rs 17,490 crore, split Rs 4,440 crore electrolyser manufacturing and Rs 13,050 crore productionProduction incentive caps of Rs 50, 40 and 30 per kg in years one to three; Mode 2A ammonia incentives of Rs 8.82, 7.06 and 5.30 per kgRs 292 crore spent by August 2026, under 1.5 per cent; no SIGHT incentive claimed or paid as at July 2026
European UnionHydrogen Bank, three auctionsSecond auction EUR 992m to 15 projects; third auction EUR 1.09bn to nine projects, about 1.1 GW; fourth round of EUR 500m opens December 2026Pilot cleared at EUR 0.48 per kg; second auction EUR 0.20 to 0.60 per kg general and EUR 0.45 to 1.88 per kg maritime; third auction EUR 0.44 to 3.49 per kgSeven second-auction projects totalling 1.9 GW withdrew; only six signed grant agreements in January 2026, about 17 per cent of awarded capacity
JapanHydrogen Society Promotion Act, via JOGMECAbout JPY 3 trillion over 15 yearsPer-unit support rates not publishedJERA, 492,144 tpa, and Mitsui, 280,000 tpa, certified 19 December 2025; about USD 6.8bn, or about 35 per cent of the envelope, on Wood Mackenzie's estimate
OmanHydrom Round 3 terms, announced 13 to 14 August 2025No envelope in the official release90 per cent reduction in land lease fees during development, reduced early royalties, up to 10 years of corporate tax exemption; no per-kilogram valueNo Round 3 award, shortlist or named bidder published as at 10 November 2026
JurisdictionInstrumentEnvelope as publishedPer-unit supportWhat has actually been paid or signed
Saudi ArabiaNone foundNone publishedNone publishedExclusive green hydrogen export right granted to ACWA Power (Zawya, July 2026): an exclusivity, not a payment
United Arab EmiratesNone foundNone publishedNone publishedNone found

India's mis­sion is the largest quan­ti­fied pro­gramme in either re­gion, and its struc­ture should be un­der­stood be­fore its size is ad­mired. It car­ries Rs 19,744 crore in total, of which SIGHT ac­counts for Rs 17,490 crore, split Rs 4,440 crore for elec­tro­lyser man­u­fac­tur­ing and Rs 13,050 crore for pro­duc­tion. Pro­duc­tion in­cent­ive caps run at Rs 50, 40 and 30 per kg in years one to three, and the Mode 2A am­mo­nia in­cent­ives are Rs 8.82, 7.06 and 5.30 per kg. Re­li­ance bid Rs 24.99 per kg for 49,000 tpa in Mode 1 Tranche II (JMK Re­search, 21 March 2025), which is to say that com­pet­it­ive bid­ding has already pushed the real­ised in­cent­ive to half the first-year cap.

The dis­burse­ment po­s­i­tion is the one that bears on a buyer. MNRE told Par­lia­ment that as at July 2026 no fa­cil­ity sup­por­ted under SIGHT had been fully com­mis­sioned, so no in­cent­ive had been claimed or paid, and that Rs 292 crore of the Rs 19,744 crore out­lay had been spent by Au­gust 2026 (Busi­ness Stand­ard, 12 Au­gust and 3 Novem­ber 2026). Under 1.5 per cent of a com­mit­ted en­vel­ope has moved. The design is not in ques­tion: de­liv­ery is un­tested, and a pro­ject re­ly­ing on the per-kilo­gram in­cent­ive re­lies on a pay­ment no party has yet re­ceived.

Under 1.5 per cent of India's committed mission outlay has been spent, and no SIGHT incentive has yet been claimed or paid.

SIGHT per-kilo­gram rates could not be ob­tained from a primary no­tice. The in­cent­ive caps and Mode 2A rates above are re­por­ted as given in sec­ond­ary sources.

GCC & India HydrogenVolge Quarterly22 •

India's non-cash sup­port may prove more valu­able than its cash. The inter-state trans­mis­sion charge waiver runs for 25 years for pro­jects com­mis­sioned on or be­fore 31 Decem­ber 2030 (MNRE and PIB PRID 2329321), which is a long-dated, mech­an­ical be­ne­fit re­quir­ing no claim pro­cess and no com­mis­sion­ing cer­ti­fic­ate from a scheme that has yet to cer­tify one. By con­trast, hub fund­ing of Rs 4 bil­lion for at least two hubs has not been de­ployed: the Au­gust 2024 tender was can­celled in July 2025. The in­stru­ments which pay auto­mat­ic­ally have per­formed; those re­quir­ing ad­min­is­tra­tion have not.

Europe pays per kilogram, and the Gulf publishes nothing

The EU Hy­dro­gen Bank is the only mech­an­ism in this sur­vey that pub­lishes a per-kilo­gram clear­ing premium, which makes it the only place where the true cost of bridging the gap can be ob­served. The pilot cleared at EUR 0.48 per kg. The second auc­tion awar­ded fixed premi­ums of EUR 0.20 to 0.60 per kg for gen­eral pro­jects and EUR 0.45 to 1.88 per kg for mari­time, totalling EUR 992m across 15 pro­jects. The third auc­tion, with res­ults on 7 May 2026, awar­ded EUR 1.09bn to nine pro­jects at about 1.1 GW, with premi­ums of EUR 0.44 to 3.49 per kg, against EUR 8.4bn bid for a EUR 1.3bn budget. The clear­ing premium has risen by a factor of seven from pilot to third auc­tion, and the over­sub­scrip­tion is six to one.

The Hy­dro­gen Bank also pub­lishes what nobody else does, which is its own at­tri­tion, and the fig­ures are severe. Seven second-auc­tion pro­jects totalling 1.9 GW with­drew (S and P Global, 18 Septem­ber 2025) and only six pro­jects signed grant agree­ments in Janu­ary 2026, rep­res­ent­ing about 17 per cent of awar­ded ca­pa­city (H2UB). A fourth round of EUR 500m opens in Decem­ber 2026. On the second auc­tion's evid­ence, an award under this scheme has roughly a one-in-six chance of be­com­ing a signed grant agree­ment, which cor­rects any read­ing of auc­tion res­ults as ca­pa­city.

Japan's en­vel­ope is the largest nom­inal fig­ure in the sur­vey, at about JPY 3 tril­lion over fif­teen years through JOGMEC, and its cer­ti­fic­a­tions are the most rel­ev­ant to In­dian ex­port­ers. JERA, at 492,144 tpa, and Mit­sui, at 280,000 tpa, were cer­ti­fied on 19 Decem­ber 2025, with Wood Mack­en­zie es­tim­at­ing about USD 6.8bn of sup­port, or about 35 per cent of the en­vel­ope. Per-unit sup­port rates are not pub­lished, so the value to a spe­cific cargo can­not be cal­cu­lated from the out­side. ACME's 405,000 tpa agree­ment with IHI is sup­por­ted by this mech­an­ism, which is the

clearest in­stance in either re­gion of a for­eign sub­sidy un­der­writ­ing an ex­port con­tract.

The Gulf is where the re­cord is thin­nest and the claims are loudest. Oman's Hy­drom Round 3, an­nounced on 13 to 14 Au­gust 2025, of­fers a 90 per cent re­duc­tion in land lease fees dur­ing de­vel­op­ment, re­duced early roy­al­ties and up to ten years of cor­por­ate tax ex­emp­tion. No per-kilo­gram value and no en­vel­ope ap­pears in the of­fi­cial re­lease. A widely re­peated USD 3.6bn in­cent­ive pack­age is a sec­ond­ary char­ac­ter­isa­tion and should not be presen­ted as of­fi­cial. For Saudi Ar­a­bia and the United Arab Emir­ates, no pub­licly quan­ti­fied pro­duc­tion sub­sidy, con­tract for dif­fer­ence or per-kilo­gram sup­port could be found in any form. The Saudi grant of ex­clus­ive ex­port rights to ACWA Power is an ex­clus­iv­ity, not a pay­ment.

The takeaway is that a buyer should value sub­sidy by its dis­burse­ment re­cord and its per-unit trans­par­ency, not by its head­line en­vel­ope. On that test, the EU Hy­dro­gen Bank is the most in­form­at­ive scheme be­cause it pub­lishes both its clear­ing premium and its at­tri­tion; Japan's is the most valu­able to an In­dian ex­porter but is opaque per unit; India's is large and en­tirely un­tested in pay­ment; and the Gulf's can­not be val­ued at all, be­cause noth­ing has been pub­lished to value. On the cur­rent re­cord, no Gulf per-kilo­gram sup­port fig­ure ex­ists in pub­lic.

The dated calendar, 2026 to 2030

The next four years contain a small number of dates that genuinely bind and a larger number that merely aspire. The most consequential is not a legal deadline at all: it is the IEA's early-2027 commercial cliff.

The cal­en­dar below sep­ar­ates what binds from what is as­pired to, and the most con­sequen­tial entry in it car­ries no legal force what­so­ever. It is the IEA's find­ing that 22 Mt of an­nounced 2030 ca­pa­city may lose any chance of be­gin­ning op­er­a­tion by 2030 if in­vest­ment de­cisions are not taken by early 2027. Everything else on the list, in­clud­ing CBAM's defin­it­ive re­gime, the end of RFNBO ad­di­tion­al­ity grand­fath­er­ing on 1 Janu­ary 2028 and the IMO ad­op­tion vote of 4 Decem­ber 2026, op­er­ates on pro­jects that take FID. The early-2027 date de­cides how many pro­jects there are for the rest of the cal­en­dar to gov­ern.

Entries marked tar­get carry no ob­lig­a­tion on any party. Entries marked bind­ing, con­trac­tual are scheme or con­tract mile­stones whose breach has com­mer­cial rather than reg­u­lat­ory con­sequences. The Hy­drom Round 3 award, short­l­ist and named bid­ders had not been pub­lished as at 10 Novem­ber 2026 and no Round 4 has been an­nounced.

GCC & India HydrogenVolge Quarterly23 •
DateEventCharacterWhom it reaches
1 January 2026CBAM definitive regime begins, hydrogen in scopeBindingEU importers, and therefore GCC and Indian ammonia, fertiliser and steel exporters commercially
31 January 2026FuelEU Maritime first annual report, covering 2025, recurringBindingOperators of ships over 5,000 gross tonnes calling at EU ports, any flag
31 January 2026Hydrom Round 3 final bids, one Duqm block up to 300 sq kmBinding on biddersOmani licensing applicants
Mid-January 2026India Carbon Credit Trading Scheme tranche 2 notified, 208 unitsBindingRefining, petrochemicals and textiles
7 May 2026EU Hydrogen Bank third auction results, nine projects, EUR 1.09bnAwardAwardees
Q2 2026Hydrom Round 3 award, indicativeTargetNo award, shortlist or named bidder published as at 10 November 2026, and no Round 4
9 to 28 August 2026India SIGHT electrolyser Tranche I scheduled commissioning, 1,500 MW across eight awardeesBinding, contractualPassed with none confirmed commissioned
30 November to 4 December 2026MEPC 85 and the resumed extraordinary session: the Net-Zero Framework adoption voteDecisionShipping, and ammonia and methanol suppliers to it
December 2026EU Hydrogen Bank fourth round opens, EUR 500mTargetBidders
Before end-2026Hintco to publish H2Global round two prices, including the AM Green per-tonne priceDisclosureEvery buyer benchmarking Indian RFNBO ammonia
2026-27India CCTS second compliance year, about 60 per cent of the required reductionBindingNotified units
1 January 2027CBAM certificate pricing moves to the weekly average ETS priceBindingEU importers
2 February 2027India SIGHT Mode 1 Tranche I, 412,000 tpa across ten awardeesBinding, contractualIncludes Reliance, ACME and Greenko at 90,000 tpa each
26 March 2027India SIGHT electrolyser Tranche II, 1,500 MW across thirteen awardsBinding, contractualAwardees
2027First production at NEOM, TA'ZIZ Ruwais and ACME Duqm; first ACME Duqm cargo to Europe; RWE offtake from AM Green beginsTargetBuyers awaiting first molecules
Early 2027The IEA's FID deadline beyond which 22 Mt of announced 2030 capacity loses any chance of 2030 operationCommercial, not legalEvery pre-FID developer in both regions
DateEventCharacterWhom it reaches
1 January 2028EU RFNBO additionality grandfathering endsBindingGCC and Indian exporters selling into EU compliance markets
1 March 2028IMO Net-Zero Framework earliest entry into force if adopted in December 2026; 4 per cent base and 17 per cent direct intensity reductions in 2028ConditionalShipping
28 February and 1 March 2028India SIGHT Mode 1 Tranche II, 450,000 tpaBinding, contractualAwardees
2028AM Green supply to Uniper begins, up to 500,000 tpaContractualUniper
July 2028Scheduled review of the EU RFNBO methodologyBinding reviewExporters holding RFNBO certification
2029Hintco deliveries from AM Green phase 2 begin; Hyport Duqm phase 1 targetContractual and targetHintco; Omani licensees
1 January 2030FuelEU zero-emission at berth in AFIR-covered EU portsBindingShip operators and port authorities
2030RED III 42 per cent industrial RFNBO and 1 per cent transport; hourly temporal correlation from 1 January 2030; CBAM factor about 51.5 per centBinding on member statesExporters into the EU
2030India NGHM 5 MMTPA; Oman 1 Mtpa; ACWA Yanbu commercial operation; ACME Odisha commissioning by July 2030 under the IHI contract for difference; India transmission waiver eligibility ends 31 December 2030TargetBoth regions

What the cal­en­dar shows is that 2026 and 2027 are dense with dates that have already been missed. The India SIGHT elec­tro­lyser Tranche I com­mis­sion­ing win­dow of 9 to 28 Au­gust 2026, cov­er­ing 1,500 MW across eight awardees, passed with none con­firmed com­mis­sioned. The Hy­drom Round 3 award, in­dic­at­ively due in the second quarter of 2026, has pro­duced no award, no short­l­ist and no named bid­der as at 10 Novem­ber 2026. QAFCO 7's re­af­firmed Q2 2026 start-up is not pub­licly con­firmed. Re­li­ance's SIGHT com­mis­sion­ing date of 9 Au­gust 2026 passed without con­firm­a­tion. A cal­en­dar whose re­cent entries have mostly been missed should be read as in­dic­at­ive for its fu­ture entries too.

The most consequential date in the next four years carries no legal force at all: it is a commercial cliff in early 2027.
GCC & India HydrogenVolge Quarterly24 •

Early 2027, and why it governs everything after it

The single most im­port­ant date on the list is the IEA's early-2027 FID dead­line, and it is im­port­ant pre­cisely be­cause it is com­mer­cial rather than legal. The arith­metic be­hind it is straight­for­ward: a pro­ject that has not taken FID by early 2027 can­not be en­gin­eered, fin­anced, con­struc­ted and com­mis­sioned in time to op­er­ate in 2030, which means 22 Mt of an­nounced pro­duc­tion loses any chance of 2030 op­er­a­tion. Noth­ing hap­pens on that date. No no­ti­fic­a­tion lapses and no pen­alty at­taches. What hap­pens is that, after it, the an­nounced tier of the pipeline stops being a 2030 sup­ply story and be­comes at best a 2032 or 2033 one.

The con­sequences for both re­gions are dir­ect. On the Gulf side, every awar­ded Omani block is pre-FID, with the en­ergy min­is­ter ex­pect­ing a first FID only in 2026 or 2027 (MEES, 7 March 2025). ACWA Power Yanbu, at about 2.5 Mtpa and tar­get­ing com­mer­cial op­er­a­tion in 2030, has FEED awar­ded and no FID. SABIC Agri-Nu­tri­ents Jubail has FID and EPC still to come. On the In­dian side, NTPC Pudimadaka is at de­tailed-pro­ject-re­port ten­der­ing, Adani Mun­dra has no FID and MNRE has stated there is no vis­ib­il­ity of pro­jects in that re­gion, and Re­li­ance's giga­fact­ory has pub­lished no 2026 up­date. Each of those sits on the wrong side of the early-2027 line as mat­ters stand.

The cliff also in­ter­acts with the European rule­book in a way that com­pounds it. A pro­ject reach­ing FID in early 2027 will not be com­mis­sioned by 1 Janu­ary 2028, and will there­fore lose the ad­di­tion­al­ity grand­fath­er­ing avail­able to elec­tro­lys­ers com­mis­sioned be­fore that date. A pro­ject miss­ing early 2027 for FID pur­poses is thus likely to miss the grand­fath­er­ing date as well, and to face hourly tem­poral cor­rel­a­tion from 1 Janu­ary 2030 with no trans­itional be­ne­fit. Two dead­lines that look in­de­pend­ent are, for most of the an­nounced pipeline, the same dead­line.

Three nearer dates are worth watch­ing for what they re­veal rather than what they re­quire. Hintco's pub­lic­a­tion of H2Global round two prices be­fore the end of 2026 will give the mar­ket its second European clear­ing price for In­dian-ori­gin RFNBO am­mo­nia, and the only in­de­pend­ent test of whether the In­dian cost base holds at European de­liv­ery. The IMO vote at the re­sumed ex­traordin­ary ses­sion on 4 Decem­ber 2026 will de­term­ine whether the largest po­ten­tial de­mand sink for am­mo­nia as a fuel ex­ists at all, with entry into force no earlier than 1 March 2028 if it passes. And the India SIGHT Mode 1 Tranche I date of 2 Feb­ru­ary 2027, cov­er­ing 412,000 tpa across ten awardees in­clud­ing

Re­li­ance, ACME and Greenko at 90,000 tpa each, will be the first real test of whether the In­dian scheme can con­vert awards into op­er­at­ing plants.

The takeaway, and the clos­ing ob­ser­va­tion of this sur­vey, is that the cal­en­dar should be used as a fil­ter rather than a fore­cast. A pro­ject that can­not name its FID date, its com­mis­sion­ing date re­l­at­ive to 1 Janu­ary 2028, its cer­ti­fic­a­tion status and its bind­ing off­take coun­ter­party is not a 2030 asset, whatever its an­nounced ca­pa­city. By the middle of 2027 the pub­lished re­cord will have answered those ques­tions for most of the pipeline in both re­gions, and the an­swers will be vis­ible without any fore­cast­ing at all. Until then, the status word, the signed off­take and the pub­lished price re­main the only three things in this sec­tor that can be re­lied upon, and in the Gulf the third of them does not yet exist. It is to be noted that the first two are avail­able to any buyer who asks for them in writ­ing, and that the an­swers are usu­ally shorter than the decks.

GCC & India HydrogenVolge Quarterly25 •

The Calls

Ten dated, falsifiable predictions for 2027: the heart of Volge Quarterly. Confidence is stated so a contrarian Medium Call and a High base case are read, and scored, differently. Each is written to be graded hit, miss or partial in the 2028 Scorecard.

The Calls: 2027, at a glance

Ten dated, falsifiable predictions for the year. The pattern is deliberate: the high-confidence Calls are the ones the physical world has already largely decided (NEOM’s completion, the Gulf’s blue-before-green sequence, India’s commissioning gap), while the genuine uncertainty sits in the corridors and the rulebook.

  • Call 1: NEOM ships first green am­mo­nia, High, Re­solves H1 2027
  • Call 2: Qatar blue starts be­fore Gulf green at scale, High, Re­solves 2026–27
  • Call 3: Ta’ziz blue reaches first pro­duc­tion, Me­dium–High, Re­solves 2027
  • Call 4: No new Gulf green FID bey­ond NEOM, Me­dium–High, Re­solves end-2027
  • Call 5: India com­mis­sions under 5% of tar­get, High, Re­solves end-2027
  • Call 6: Fer­til­iser is India’s first green de­mand at scale, High, Re­solves 2027
  • Call 7: The premium stays above 1.5× blue, Me­dium–High, Re­solves end-2027
  • Call 8: First H2Global cargo lands at Rot­ter­dam, Me­dium–High, Re­solves 2027
  • Call 9: India→Japan beats Gulf→NE Asia, Me­dium, Re­solves 2027–28
  • Call 10: RFNBO forces an EU-ex­port MoU to lapse, Me­dium, Re­solves end-2027

Calls one to three

The reasoning behind each Call, with confidence and resolution date. The first three concern the Gulf, where the near-term outcome is largely set: NEOM ships, and blue precedes green.

1. NEOM ships first green ammonia

NEOM’s He­lios plant pro­duces its first green am­mo­nia dur­ing 2027. The tar­get has already slipped from end-2026, and Air Products guides to mid-2027.

Con­fid­ence: High · Re­solves H1 2027

Con­struc­tion is com­plete and 100% of out­put is sold to Air Products for 30 years, so the risk is ramp and com­mis­sion­ing rather than de­mand or com­ple­tion. ACWA Power told ana­lysts on 6 Au­gust 2026 that com­mer­cial op­er­a­tions are set for 2027 [7][8][5].

2. Qatar blue starts before Gulf green at scale

Qatar’s Am­mo­nia-7 (blue) starts up be­fore any GCC green am­mo­nia reaches scale : the Gulf’s near-term pro­du­cing volume is blue, not green.

Con­fid­ence: Me­dium · Re­solves 2026–27

Am­mo­nia-7 is under con­struc­tion, but its tar­get moved to the second quarter of 2026 and no start-up has been an­nounced, against a 37% fall in Qatari ni­tro­gen ex­ports in the first half of 2026. Green FIDs bey­ond NEOM re­main thin; the re­gion de­car­bon­ises ex­ist­ing am­mo­nia faster than it builds green ex­port [11].

3. Ta’ziz blue reaches first production

The UAE’s Ta’ziz blue-am­mo­nia plant at Ruwais reaches first pro­duc­tion in 2027, on the Mit­sui off­take into Japan and Asia.

Con­fid­ence: High · Re­solves 2027

Con­struc­tion began in the third quarter of 2024 with a named off­taker; the sched­ule is tight but the struc­ture is com­plete, and $1.39bn of fin­an­cing closed on 4 Novem­ber 2026 with 2027 op­er­a­tions re­af­firmed [2][21].

Calls four to six turn from the Gulf’s com­ple­tions to its FID drought and to India’s two de­fin­ing facts: the com­mis­sion­ing gap and the fer­til­iser de­mand an­chor.

4. No new Gulf green FID beyond NEOM

No new GCC green-hy­dro­gen megapro­ject bey­ond NEOM reaches final in­vest­ment de­cision with bind­ing off­take by end-2027.

Con­fid­ence: Me­dium–High · Re­solves end-2027

Oman’s blocks are auc­tioned ahead of de­mand, Mas­dar’s green tar­get has slipped past 2030, and in Au­gust 2026 it can­celled a 100 MW elec­tro­lyser for Em­steel’s Musaf­fah com­plex and re­dir­ec­ted 6 GW of solar from green am­mo­nia to data centres, and the bind­ing-off­take bar that took NEOM to FID has not been cleared again [1][3][9].

5. India commissions under 5% of target

India com­mis­sions less than 5% of its 5-MTPA-by-2030 green-hy­dro­gen tar­get by end-2027.

Con­fid­ence: High · Re­solves end-2027

About 0.16% was com­mis­sioned by Feb­ru­ary 2026 on 1.3% of the budget; even rapid ac­cel­er­a­tion leaves

GCC & India HydrogenVolge Quarterly26 •

the com­mis­sioned base far below 5% within the win­dow [4].

6. Fertiliser is India’s first green demand at scale

India’s green-am­mo­nia-to-fer­til­iser pro­gramme be­comes the coun­try’s first at-scale green-hy­dro­gen de­mand, ahead of any ex­port use.

Con­fid­ence: High · Re­solves 2027

670,000 tonnes a year was signed with 11 of the 13 units to which 724,000 tonnes a year was al­loc­ated, on ten-year terms: con­trac­tual, do­mestic de­mand that be­gins de­liv­er­ing in 2027 [27].

Calls seven and eight con­cern the eco­nom­ics and the first European im­port: the premium that will not close, and the auc­tion-backed cargo that will land.

7. The premium stays above 1.5× blue

The green premium does not close to below 1.5 times blue in any Gulf or India mer­chant pro­ject by end-2027.

Con­fid­ence: Me­dium–High · Re­solves end-2027

Green runs 2 to 3 times blue, and CareEdge puts re­new­able hy­dro­gen at 1.5 to 5 times un­abated fossil; elec­tro­lyser capex rose about 57% since 2022; no un­sub­sid­ised mer­chant pro­ject has a path to 1.5× within the year [13].

8. First H2Global cargo lands at Rotterdam

The first H2Global / Fer­ti­globe green-am­mo­nia cargo lands in Rot­ter­dam in 2027 : Europe’s first auc­tion-cleared im­port.

Con­fid­ence: Me­dium · Re­solves 2027

19,500 tonnes is sched­uled for 2027 at €1,000 a tonne under a gov­ern­ment-back­stopped con­tract, but the Haber-Bosch plant is only sched­uled to be op­er­at­ing dur­ing 2027 and at full ca­pa­city in early 2028, and the Port of Rot­ter­dam an­ti­cip­ates com­mer­cial activ­ity in 2028 [29].

The final two Calls carry the year’s genu­ine un­cer­tainty: which cor­ridor de­liv­ers first, and whether Europe’s rule­book claims a cas­u­alty.

9. India→Japan beats Gulf→NE Asia

India se­cures a second cer­ti­fied green-am­mo­nia ex­port cor­ridor, on bind­ing terms, be­fore any Gulf-to-North­east-Asia green off­take de­liv­ers. The ori­ginal Call, that ACME reaches Japan ahead of the Gulf, has been re­tired: its premise res­ted on about 405,000 tonnes a year from 2027, where the con­tract for

dif­fer­ence in fact cov­ers 228,000 tonnes a year from Septem­ber 2030.

Con­fid­ence: Me­dium · Re­solves 2027–28

ACME’s Odisha cer­ti­fic­a­tion stands but de­liv­ers at the end of the dec­ade, so it can­not grade a 2027 race. Com­pet­ing Gulf green routes still lack bind­ing de­liv­ery dates, and the Gulf's ex­port rout­ing is now it­self in ques­tion [30].

10. RFNBO forces an EU-export MoU to lapse

EU RFNBO com­pli­ance, rather than gen­eral vi­ab­il­ity, forces at least one an­nounced Gulf or India EU-ex­port memor­andum to lapse or re­struc­ture by end-2027. Re­treats on techno-com­mer­cial grounds do not count: INOX Air Products aban­doned a $3bn In­dian green am­mo­nia pro­ject in Oc­to­ber 2026 and Mas­dar can­celled an Em­steel elec­tro­lyser in Au­gust 2026, neither on cer­ti­fic­a­tion grounds.

Con­fid­ence: Me­dium · Re­solves end-2027

Cer­ti­fic­a­tion is hard and mer­chant European de­mand is thin above the €1,000/t auc­tion price; a non-com­pli­ant an­nounced route is the like­li­est cas­u­alty [32][5].

Reading the confidence bands

Four Calls are High, four Me­dium–High, two Me­dium. The High Calls are near-cer­tain­ties the year merely con­firms; the Me­dium Calls are where the edi­tion takes real risk, and where the 2028 Score­card will most test its judge­ment.

How the Calls are made

The Calls are reasoned judgements, not forecasts dressed as certainties. Each is written to a single standard: dated, falsifiable, sourced, and gradable by an outsider without access to the author.

A Call earns its place only if it can fail. “Green hy­dro­gen will grow” is not a Call; “India com­mis­sions less than 5% of its 5-MTPA tar­get by end-2027” is, be­cause a single num­ber in Decem­ber 2027 settles it. Every Call names the year it re­solves, the threshold that de­cides it, and the evid­ence it rests on. Where the evid­ence is a memor­andum rather than a bind­ing con­tract, the Call is writ­ten to ac­count for the dif­fer­ence.

The confidence bands

Con­fid­ence is stated ex­pli­citly (High, Me­dium–High, Me­dium, Low) so that a con­trarian low-con­fid­ence Call and a high-con­fid­ence base case are read, and scored, dif­fer­ently. A High Call that hits earns little credit; a Me­dium Call that hits earns more, and a High Call that misses is the most dam­aging out­come of all.

GCC & India HydrogenVolge Quarterly27 •

The bands are a claim about the au­thor’s cer­tainty, not a hedge.

How they are graded

The 2028 edi­tion opens with the Score­card: each of these ten Calls marked hit, miss or par­tial, with a run­ning hit-rate by con­fid­ence band. A for­ward-look that re­fuses to mark its own home­work is a bro­chure; Volge Quarterly marks it. No Score­card ap­pears in this volume; it opens the ac­count­ab­il­ity loop the next edi­tion closes.

The standard

Dated, falsifi­able, sourced, grad­able. A Call that can­not be proven wrong by a spe­cific date is not pub­lished.

The year, read

The year by domain, three scenarios for how it resolves, the operator’s toolkit, and the reference annex (project data, numbered sources and a glossary) against which every figure in this edition can be checked.

By domain: technology, markets, regulation, delivery

The same year reads differently through each lens. Technology says the machine got more expensive; markets say demand contracted; regulation says the rulebook hardened; delivery says almost nothing has been built. All four are true at once.

Technology

The elec­tro­lyser is the story, and it moved the wrong way: me­dian capex rose about 57% between 2022 and 2024, and a four-fold cost gap opened between Chinese al­kaline stacks (~$600/kW) and West­ern PEM (~$2,500/kW) [GFJ, 2026]. Am­mo­nia re­mains the car­rier of choice, li­quid at −33°C against −253°C for hy­dro­gen. The tech­no­logy works; its eco­nom­ics re­gressed.

Markets

The de­fin­ing mar­ket fact is con­trac­tion: the an­nounced 2030 pipeline fell 49 to 37 Mtpa and then to 27 Mt [IEA, Oc­to­ber 2026], and new off­take has been flat near 1.7 Mt with only about a fifth under firm con­tract. The Gulf’s near-term volume is blue; India’s de­mand is do­mestic and policy-made. Mer­chant mar­kets barely exist.

Regulation

Europe’s RED III and, from Janu­ary 2026, the car­bon bor­der levy make the RFNBO stand­ard the ex­port pass­port. Japan and Korea run con­tracts-for-dif­fer­ence; India has no eco­nomy-wide con­sump­tion man­date. Policy, not price, is the de­mand.

Delivery

The hard­est lens. NEOM is built and com­mis­sion­ing; Qatar and Ta’ziz will ship blue; India has com­mis­sioned 0.16% of its tar­get. De­liv­ery is where an­nounce­ments meet the ground, and in 2027 the ground is mostly still empty.

The one-line read

Tech­no­logy re­gressed, mar­kets con­trac­ted, reg­u­la­tion hardened, de­liv­ery lagged. The year re­wards the few pro­jects that solved off­take be­fore they began.

Three scenarios for 2027

One year, three ways it can resolve. The base case is that 2027 confirms the physical facts already in train; the bull and bear cases turn on offtake and on whether a flagship slips.

Bull The mo­lecule ships and de­mand hardens NEOM pro­duces on sched­ule and ramps faster than feared; Qatar and Ta’ziz start up on time; the first H2Global cargo lands at Rot­ter­dam and ACME’s am­mo­nia reaches Japan; India’s fer­til­iser de­liv­er­ies begin and a second Gulf green pro­ject reaches FID with bind­ing off­take. The premium nar­rows at the mar­gin. Prob­ab­il­ity: lower. It re­quires off­take to solve faster than the 1.7 Mtpa trend sug­gests. Base Com­ple­tions land, the pipeline stays thin NEOM ships first green am­mo­nia in H1 2027; blue pre­cedes green across the Gulf; India com­mis­sions well under 5% of tar­get but be­gins fer­til­iser de­liv­er­ies; the first Rot­ter­dam cargo lands; no new Gulf green megapro­ject reaches FID; the premium does not close. The year con­firms the facts already set. Prob­ab­il­ity: highest. Bear A flag­ship slips and de­mand stalls NEOM’s first pro­duc­tion slips bey­ond 2027; an an­nounced Gulf or In­dian flag­ship is de­scoped or shelved; H2Global or a cor­ridor cargo is delayed; India’s com­mis­sion­ing gap widens as sub­sidy dis­burse­ment lags. The con­trac­tion in the pipeline ac­cel­er­ates. Prob­ab­il­ity: ma­ter­ial, given a pipeline that already shrank once.

Scen­arios are the au­thor’s fram­ing of the same sourced evid­ence, not sep­ar­ate fore­casts. The base case car­ries the weight of the ten Calls; the bull and bear mark the range around them.

GCC & India HydrogenVolge Quarterly28 •

The watchlist: the signals that seed next year’s Calls

The signals to watch through 2027, each of which will shape or settle a Call and seed the 2028 edition. These are the events that, more than any announcement, will tell an operator where the sector is actually going.

NEOM He­lios first-pro­duc­tion date, and the shape of its ramp against name­plate through 2027. Qatar Am­mo­nia-7 and Ta’ziz start-up con­firm­a­tions, the blue-be­fore-green se­quence in fact. Any new Gulf green-hy­dro­gen FID with bind­ing, full-volume off­take bey­ond NEOM. Oman Round 3 Duqm awards and the SalalaH2 final in­vest­ment de­cision, both due in 2026. India’s com­mis­sioned ca­pa­city and Mis­sion dis­burse­ment rate, the gap between award and plant. First de­liv­er­ies under the 670,000 t/yr fer­til­iser off­take signed in March 2026. The first H2Global / Fer­ti­globe cargo into Rot­ter­dam, and its landed price. ACME/IHI first de­liv­ery to Japan under the JOGMEC con­tract-for-dif­fer­ence. Any an­nounced Gulf or In­dian EU-ex­port memor­andum that lapses or re­struc­tures on RFNBO grounds. Elec­tro­lyser capex dir­ec­tion: whether the 2022–24 rise re­verses.

Next year

The 2028 edi­tion opens with the Score­card: each of this year’s ten Calls graded hit, miss or par­tial, with a run­ning hit-rate by con­fid­ence band. A for­ward-look that re­fuses to mark its own home­work is just a bro­chure; Volge Quarterly marks it.

De­veloper, IEA, Hy­drom, SECI/MNRE, Mer­com and Am­mo­nia En­ergy dis­clos­ures (2023–26). Fig­ures marked to verify in the body carry the same caveat here. Name­plate ca­pa­cit­ies at full build un­less stated.

Project data appendix

The projects referenced in this edition, with capacity, status and offtake on one page. Green and blue are distinguished; binding offtake is marked, and memoranda are not counted as anchors.

ProjectTypeCapacityOfftakeStatus / date
NEOM Helios (Saudi)Green>1.2 Mtpa NH₃; ~600 t/d H₂Air Products, 100%, 30 yrs (binding)Built; first production mid-2027
Qatar Ammonia-7Blue1.2 Mtpa NH₃QAFCO/QatarEnergyStart-up 2026
Ta’ziz (UAE)Blue1.0 Mtpa NH₃Mitsui (Japan/Asia)First prod. 2027
Masdar green (UAE)Green1 Mtpa targetEuropean JVsDelayed past 2030
HyPort Duqm (Oman)Green500 MW; ~60,000 t/yrOQ/Uniper/DEMEPhase 1 ~2026
SalalaH2 (Oman)Green400 MW; ~$1bnOQ/LindeFID 2026
ACME Duqm (Oman)Green900,000 t/yr NH₃Not disclosed bindingPhased; demand-constrained
NTPC Pudimadaka (India)GreenHub; 70,000 t/yr NH₃ @ ₹51.80/kgSECI/fertiliserPact 31 Mar 2026
AM Green KakinadaGreen90,000 t/yr (SECI T-II award)SECI productionAwarded
Reliance JamnagarGreen~139,000 t/yr + 300 MWSECI productionUnder build
ACME (India)Green90,000 t/yr + ~370,000 t/yr NH₃IFFCO Paradeep (record ₹49.75/kg); Japan via IHIAwarded
Fertiglobe H2GlobalGreen19,500 t (2027) → 397,000 t cum.H2Global auction, €1,000/tFirst cargo 2027
India fertiliser (SECI)Green670,000 t/yr NH₃ with 11 units; 724,000 t/yr allocated across 1310-yr, ₹49.75–64.74/kg (binding)Signed 31 Mar 2026
GCC & India HydrogenVolge Quarterly29 •

Sources and glossary

Numbered sources

[1] IEA, Global Hy­dro­gen Re­view 2025 (9 Dec 2025) [3] Bloomberg, “Mas­dar Delays Green H2 Tar­get Bey­ond 2030” (28 Oct 2024) [4] Busi­ness Today, “India’s green hy­dro­gen real­ity check” (11 Jun 2026); MNRE [5] Am­mo­nia En­ergy Assoc., NEOM fin­an­cial close and 30-year off­take (2023) [6] NEOM / PRNewswire, $8.4bn fin­an­cial close (2023) [7] Oil & Gas Middle East, NEOM ~90% built (2026) [8] Smart Water Magazine, NEOM first pro­duc­tion 2026 [9] GH2.org, Oman na­tional pro­gramme (2025) [10] gas­world / PRNewswire, Hy­drom Round 3 (2025) [11] MEES, Qatar Am­mo­nia-7 (29 Nov 2024) [12] MNRE, Na­tional Green Hy­dro­gen Mis­sion PDF (Jan 2023) [13] Green Fuel Journal, Cost eco­nom­ics (2026) [14] BloombergNEF, Elec­tro­lyser cost bands (9 Aug 2023) [15] PV Tech, Al Dhafra $0.0135/kWh (2020) [16] RenewEconomy, Saudi solar 1.04c/kWh (2021) [17] ACWA Power, NEOM equity (2023) [18] thyssen­k­rupp, >2 GW elec­tro­lysis (2023) [19] gas­world, ACWA ex­port rights (2023) [20] Am­mo­nia En­ergy, SalalaH2 FID 2026 [21] ADNOC / Mit­sui / MEES, Ta’ziz blue am­mo­nia (2024) [22] En­er­get­ica India, SECI pro­duc­tion auc­tion win­ners (3 Jan 2024) [23] Re­new­able Watch, SECI pro­duc­tion Tranche II (20 Mar 2025) [24] JMK Re­search, SECI Tranche II ana­lysis (2025) [25] Re­new­able Watch, Elec­tro­lyser-man­u­fac­tur­ing auc­tion, T-I (Jan 2024) [26] Re­new­able Watch, Elec­tro­lyser-man­u­fac­tur­ing auc­tion, T-II (Sep 2024) [27] Mer­com, SECI 724,000 tpa green am­mo­nia (31 Mar 2026) [28] Down To Earth, Green Steel Tax­onomy (30 Dec 2024) [29] Fer­ti­globe / Port of Rot­ter­dam / H2Global, Pilot auc­tion (Jul 2024) [30] Am­mo­nia En­ergy, ACME–IHI Japan cer­ti­fic­a­tion (3 Jul 2026) [31] EU Hy­dro­gen Ob­ser­vat­ory, RED III (in force Nov 2023) [32] European Com­mis­sion, Re­new­able-hy­dro­gen del­eg­ated acts (20 Jun 2023) [33] REPowerEU / European Com­mis­sion, 20 Mt re­new­able H2 by 2030 (2022) [34] European Com­mis­sion, CBAM defin­it­ive re­gime (from 1 Jan 2026) [35] CSIRO HyResource, Japan JOGMEC CfD (2025) [36] Am­mo­nia En­ergy, Korea CHPS auc­tion (16 Dec 2024)

Glossary

RFNBO. Re­new­able Fuel of Non-Bio­lo­gical Ori­gin: the EU RED III class of hy­dro­gen/de­riv­at­ives that counts to­ward re­new­able tar­gets; the de-facto ex­port pass­port.

All fig­ures were re­freshed to Novem­ber 2026 and are at­trib­uted in­line by source and year. Source num­ber­ing fol­lows Volge’s re­search dossier. Volge Quarterly is gov­erned by Volge’s Morph­eus stand­ard; this edi­tion is not in­vest­ment ad­vice.

RED III. EU Re­new­able En­ergy Dir­ect­ive (in force Nov 2023): 42% of in­dus­trial hy­dro­gen RFNBO by 2030, 60% by 2035.

CBAM. Car­bon Bor­der Ad­just­ment Mech­an­ism: the EU car­bon levy on im­ports; defin­it­ive re­gime from 1 Jan 2026, reach­ing hy­dro­gen and am­mo­nia.

Grey / blue / green. Hy­dro­gen from un­abated gas (grey), gas with car­bon cap­ture (blue), or elec­tro­lysis on re­new­able power (green).

FID. Final In­vest­ment De­cision: the point at which a pro­ject is com­mit­ted and fin­anced.

Take-or-pay / MoU. A bind­ing con­tract ob­li­ging a buyer to pay for volume, versus a non-bind­ing memor­andum of un­der­stand­ing.

SIGHT. Stra­tegic In­ter­ven­tions for Green Hy­dro­gen Trans­ition: India’s in­cent­ive scheme under the Mis­sion (via SECI).

NGHM. India’s Na­tional Green Hy­dro­gen Mis­sion (ap­proved Jan 2023): ₹19,744 cr, 5 MTPA by 2030.

CfD. Con­tract-for-Dif­fer­ence: a gov­ern­ment-back­stopped price sup­port, used by Japan (JOGMEC) and Korea (CHPS).

H2Global. EU-backed im­port auc­tion mech­an­ism; cleared green am­mo­nia at €1,000/t into Rot­ter­dam.

Mtpa / tpd. Mil­lion tonnes per annum; tonnes per day.

Al­kaline / PEM. The two main elec­tro­lyser tech­no­lo­gies: cheaper al­kaline (often Chinese) and West­ern PEM.

GCC & India HydrogenVolge Quarterly30 •
GCC & India Hydrogen

The world’s announced 2030 pipeline shrank for the first time: 49 to 37 million tonnes in a single year, and to 27 million tonnes in the 2026 review, and barely a tenth of it has reached an investment decision.

Version · VSP-OTG-005 · 2026
volgePublished
every quarter
About Volge Quarterly

Volge Quarterly is Volge's signature series, published every quarter for enterprise customers. Each edition takes one subject, sets out where it currently stands on the published record, and makes a set of dated, falsifiable judgements on where it is going, written to give a buyer something firmer than a forecast: every figure carries its source and its date, every judgement carries the date on which it resolves, and the following year's edition grades each one hit, missed or partial.

Where a figure is not published, the edition says so rather than estimating it. Where published sources disagree, both are given and the disagreement is stated rather than averaged away. A number that does not survive checking is corrected here rather than repeated.

The edition carries no recommendation of any supplier and no offer of service. Where a vendor, platform or deployment is named it is because it is part of the published record of the subject.

Terms of use

This edition may be shared freely. It may not be altered or republished without permission, and figures carry their stated basis and date. Names and marks appearing in it are the property of their respective owners.